•  Open the plastic bag containing the transport container.1x Wall Power Supply (5V/3A)
•  Remove the three pairs of nuts and screws holding the CEM.
•  Carefully remove the CEM assembly by pulling the flange upwards. The cables and the CEM mount 

may touch the opening, but do not rotate the assembly before the CEM funnel has fully cleared the 

opening.

•  Remove the viton gasket. Again, touching the cables or CEM mount with the gasket is not a problem, 

but keep away from the CEM funnel.

The funnel at the front of the CEM should be protected from exposure to particle 

contamination. While transporting the CEM outside the container keep the funnel 

pointing downwards or inside a suitable container. Larger particles can be removed by 

carefully using tweezers.

•  Install the CEM by placing a copper gasket on the base flange and inserting the CEM assembly into an 

appropriate DN40CF flange opening. Take care not to touch the walls or other obstacles with the CEM 

funnel and do not pinch the cables between the flange edges.

•  After installation of the CEM assembly, evacuate the chamber. This is a high-pressure channeltron, do 

not perform bakeout.

•  At this point, you can perform some basic resistance checks, 

see Chapter 4.1

.

•  Keep the transport container in case the CEM must be sent back for repair or modification. It can also 

be used for storing the detector temporarily when not installed in a vacuum chamber.

A dry atmosphere/rough vacuum is recommended in both cases

See Chapter 5.1

 for additional information.

•  High-Pressure channeltron assembly: Do not perform bakeout when using the 

standard mount.

•  Maximum operating temperature: 70 °C

•  Maximum ambient pressure with high voltage applied:  < 1E-3 mbar

Note

The CEMs should be kept under vacuum or in protective atmosphere if possible. 

Alternatively use a dry atmosphere. Water contamination may change gain characteristics 

over time. The best long term storage environment is an oil free vacuum in the 10E-2 

mbar range or better.  The transport container is not designed for a long term storage of 

the CEMs. 

Summary of Contents for CEM 4230

Page 1: ...CEM 4230 Detector Setup Manual CEM 4230 Detector Setup Manual...

Page 2: ...131 62716 0 fax 49 6131 62716 29 email info surface concept de web www surface concept de All rights reserved No part of this manual may be reproduced without the prior permission of Surface Concept G...

Page 3: ...lation 5 3 1 Initial Inspection 5 3 2 Installation 5 3 2 1 Mounting the CEM 5 3 2 2 Cabling and High Voltage 7 4 Operation of the CEM 9 4 1 Start Up Procedure for First Time Operation 9 4 1 1 Basic Ch...

Page 4: ...tor Follow this information to ensure a proper functioning of the detector The caution symbol marks warnings which are given to prevent an accidentally damaging of the detector or the readout system D...

Page 5: ...contact SURFACE CONCEPT immediately Please check the delivery according to the packing list see Table 1 for completeness CEM 4230 Detector Setup in transport container delivered under Argon atmospher...

Page 6: ...h the walls or other obstacles with the CEM funnel and do not pinch the cables between the flange edges After installation of the CEM assembly evacuate the chamber This is a high pressure channeltron...

Page 7: ...Connect any HV Supply to the 3 SHV feedthroughs of the CEM base flange Connect any HV Supply to the U DET SHV connector of the decoupling box In case of using a Surface Concept CEM Decoupling Box mou...

Page 8: ...ition counting and or time resolved measurements Connect any HV Supply to the 3 SHV feedthroughs of the CEM base flange Finish the complete cabling before any HV supplies and or pulse processing devic...

Page 9: ...d ground The only measurable resistance should be between R U IN U OUT of several 10 MOhm of R U IN U DET of several 10 MOhm and of R U OUT R DET of 1 MOhm All resistances towards ground should be inf...

Page 10: ...eforeperforming any changes of the cabling 4 2 Standard Operating Procedure Use this procedure later on for all operations when the detector has already been operated in vacuum before and has not been...

Page 11: ...11 CEM 4230 Detector Setup Manual 4 3 Bake Out Procedure This high pressure channeltron assembly is not intended for bake out...

Page 12: ...required Alternatively store the CEMs in argon dry air or even better in vacuum Water may lead to a reduction in the work function resulting in a higher gain During the burn in after having been stor...

Page 13: ...13 CEM 4230 Detector Setup Manual 6 List of Figures Figure 1 A CEM assembly mounted to the transport container and after removal 5 Figure 2 Possible connection scheme of the CEM 4230 Detector Setup 7...