3.6. Power Up
1)
Switch on the inverter by pressing the green start button.
2)
Switch on the Battery Isolator.
3)
Switch on the Solar Isolator if solar is used.
4)
The system should now start running.
3.7. Setting Up a Lithium Battery
The first thing to do after the system power-up is to check that the lithium battery is
communicating correctly with the inverter. If it is not communicating with the inverter,
you need to set up the battery on the Battery Setup screen before moving forward with
the commissioning.
The startup should be performed by a qualified engineer since there is a high
risk of electruction while the covers are off.
WARNING