7 Commissioning
49
Step 8
Set the inverter time as per local time.
Incorrect time setting will affect the data
logging.
Press
to move the cursor and
Press
to set the specific time and date.
Press
ENTER
to confirm setting.
Step 9
After configuring all parameters, there will be
a “setting confirmation” screen. Check whether
all above-mentioned parameters are correct.
Confirm by
Pressing
ENTER
. Cancel by
Pressing
ESC
and reset.
Step 10
Inverter will enter into startup process.
Observe the status of LED indicators and the
LCD main screen. If commissioning succeeds,
the “RUN” indicator will be on and “Run” will be
displayed on the “State” area.
If commissioning fails, the “FAULT” indicator will be on and “Fault” will occur on the
display.
Press
to view “current fault” information. Remove the existing fault and
then repeat the commissioning procedures.