Installation Manual
42
After drilling holes on the bottom plate of the inverter, the remove all burrs and take
effective protection measures (waterproof terminal is optional) to prevent the cables
from scratch or abrasion.
Seal the gaps of the cable entries and around the cover plate by waterproof and
fireproof materials.
If there are communication and power distribution cable entries on the bottom of the
inverter, seal the gaps by using fireproof mud.
The sealing by fireproof mud should meet the waterproof and dustproof requirement.
Reassemble the insulation covers and protective covers removed before cable
connection.
The cable entries of the inverter are equipped with aluminum cover plate. Please do
not use cover plate of other materials to seal the cable entries. For details, consult
Sungrow.
7.14
Installation Checklist
After installation, perform a thorough check.
Keep check records and take corresponding measures when necessary.
Mechanical Installation
□
The inverter is free of damages, scratches, or deformations.
□
The inverter has been fixed properly to the floor
□
The clearance around the inverter is sufficient
□
The ambient temperature, humidity, and ventilation meet requirements
□
The cooling air circulates smoothly
□
The protective enclosure seal is intact and reliable
Electrical Installation
□
The inverter is grounded properly
□
The grid voltage matches the nominal output voltage of the inverter
□
Phase sequences on the grid side are consistent, and fastening torque meets
requirement
□
The polarity on the DC side is correct, and fastening torque meets requirement
Electrical Installation
□
The communication cable is connected correctly and kept at a distance from
other cables
□
Cable markings are correct and clear
□
The insulation protective cover is intact and reliable, and the warning labels are
clear and firmly attached
Others
□
All the unused cables are tightened by using insulation belts
□
No tools, foreign objects or dust are left inside the inverter
□
No condensation or ice is in the cabinet