Improper foundation construction may affect the placement of the MV Station, open & close
of the door, and future maintenance. Therefore, the foundation must be designed and
constructed according to the related standard. The dimensions and weight of the MV Station,
the cable route, and the future maintenance should be considered at all times.
The following conditions must be met:
The bottom of the foundation should be firm enough.
The foundation should be at higher than the ground level on site to prevent the rain
from damaging the base or penetrating into the MV Station.
Sufficient cross-sectional area and depth of the foundation should be maintained. The
depth is designed according to local soil conditions.
Cable route should be taken into account.
According to the cable design of MV Station and for easy electrical
connection, please establish cable trenches on the bottom of the MV Station,
i.e. reserve the cable trenches inside the foundation and pre-bury the wire
pipes.
The dirt dug out should be cleared immediately.
5.3.3 Recommended Foundation Construction Plan
The following conditions must be fulfilled:
The bottom of the foundation should be firm enough.
The foundations must be suitable for the weight of the MV Station.
The foundation should be at least 100mm higher than the solid ground on site to
prevent the rain from damaging the base or penetrating into the MV Station.
Sufficient cross-sectional area and depth of the foundation should be maintained. The
depth is designed according to local soil conditions.
Cable route should be taken into account.
Overall construction effect is shown below.