Step 4:
inspect whether the wires are correctly and firmly connected, especially whether the positive and
negative input poles of the battery are correct, whether the positive and negative input poles of PV are correct,
whether AC input is inaccurately connected to AC output terminal.
Step 5:
install protective cap of terminal
Step 6:
Start solar charge inverter
At first close the breaker at the battery end, and then press the rocker switch at the lower left side of the machine
to
“
ON
”
state,
“
AC/INV
”
indicator light flashes, indicating normal operation of inverter. Afterwards,
close breakers of photovoltaic array and mains supply. In the end, after AC output is normal, turn on AC load
one by one to avoid protection action generated by great instant impact owing to simultaneous turnon of loads.
The solar charge inverter operates normally in accordance with set mode.
Note: if power is supplied to different AC loads, it is suggested to turn on the loads with great impact current,
and then turn on the load with little impact current after the load operates stably.
Note: in case of abnormal operation of solar charge inverter or abnormal display of LCD or indicator light, refer
to Chapter 6 for troubleshooting.