ELECTRIC FURNACE PRESTART CHECKLIST
❏
1. REMOVE PACKING MATERIALS FROM LEFT SIDE OF BLOWER
❏
2. CONFIRM DIP SWITCH SETTINGS AS FOLLOWS
❏
3. DISCHARGE AIR SENSOR INSTALLED AFTER A/C COIL
❏
4. LOW HEAT/HIGH SELECT SWITCH SET TO HIGH HEAT. (UNLESS
OTHERWISE SELECTED)
❏
5. INITIATE CALL FOR HEAT.
ELEMENT LEDS ILLUMINATE AS ELEMENTS TURN ON,
FAN MOTOR SPEED INCREASES AS ELEMENTS TURN ON
RECORD FULL AMP DRAW AT FULL POWER
❏
6. CANCEL CALL FOR HEAT
ELEMENT LEDS TURN OFF.
APPROXIMATELY 1 MINUTE LATER, FAN TURNS OFF
(PROVIDED THAT CONTINUOUS FAN HAS NOT BEEN SELECTED)
❏
7. INTERRUPT POWER TO OUTDOOR CONDENSOR.
INITIATE CALL FOR COOLING,
ONCE FURNACE FAN IS RUNNING, CONFIRM 24 VOLT OUTPUT AT Y
AND C AT COMP RELAY
RECONNECT POWER TO CONDENSOR IF TEST SUCCESSFUL
NOTE: MAIN CONTROL DELAY INTERVAL BETWEEN COOLING
CYCLES MAY DELAY COOLING RESTART UP TO 5 MINUTES.
❏
8. CANCEL CALL FOR COOLING
APPROXIMATELY 1 MINUTE LATER, FAN TURNS OFF
(PROVIDED THAT CONTINUOUS FAN HAS NOT BEEN SELECTED)