Installation
8
Fig. 4 – Super High-Capacity
INSTALLATION
Hanger Brackets
Standard and Hi-Capacity with Rigid Mount
1. Divide circumferences of
center fill ring into three (3)
equal
parts.
Position
brackets so Spredway will
be level. If holes are
provided in peak ring,
Steps 1 and 2 may be
eliminated.
2. Mark and drill 5/16” holes.
Bolt brackets into place.
3. Holes have been provided
in rigid mount hanger
brackets to allow for
multiple Spredway
positions. Bolt Spredway
to brackets using 5/16 x 1"
bolts. Ensure Spredway is
level.
REF #
DESCRIPTION
QTY. COMP. #
1
Rigid hanger, 2006 (3)
1 set
G0197A
2
Peak ring bracket (Rigid) (3) 1 set
G0196A
3
Bolt, 5/16 - 18 x 1”, PLT
18
J0527
4
Lock washer, 5/16", PLT
18
J1200
5
Hex nut, 5/16” - 18
18
J1002
6
Flat washer, 5/16"
18
J1111
Super Hi-Capacity
1. Divide circumferences of center fill ring into three (3)
equal parts. Position brackets so Spredway will be
level.
2. Mark and drill 5/16" holes. Bolt brackets into place.
3. Place hangers into slots on Spredway cone straps
and lower Spredway into opening*. Place hangers
into slots on brackets bolted to fill ring. Ensure
Spredway is level.
REF. #
DESCRIPTION
QTY. COMP. #
1
Hanger, 15" (3)
1 set G0212A
Hanger, 26" (3)
1 set G0213A
2
Adapter hanger bracket (3) 1 set G0125A
3
Bolt, 5/16 - 18 x 1”, PLT
6
J0527
4
Lock washer, 5/16"
6
J1200
5
Nut, 5/16" - 18
6
J1002
*If bin’s fill ring is too small for Spredway to fit through, use a winch to raise it from inside of bin.
Fig. 3 – Standard and
Hi-Capacity w/ rigid
mount