- 13 -
d) With the vessel on its side screw the Mainsboost vessel connector
provided in the upsteam line-in kit, into the tank elbow using suitable
thread seal such as PTFE tape or liquid thread lock (see Fig. 16).
e Cut a piece of 28 mm dia. copper pipe to the following minimum length,
ensuring clearance of the base.
Pipe length:
MB 100SV = 210 mm MB 200SV = 270 mm
MB 300SV = 270 mm
MB 130SV = 210 mm MB 250SV = 270 mm
MB 450SV = 340 mm
f) Fit the isolating valve provided to the tail.
NOTE: It is good practice to install a drain port between the isolation valve and the
vessel.
c) Remove the plastic skirt by rotating anti-clockwise to unclip and discard.
NOTE: Horizontal mounting is available for the steel MB 200 SH
and MB 250 SH vessels only.
NOTE:
Do not
forget if a water softener is to be installed this has
to be included in this pipe run, and additional space must be
allocated for this.
Do not
fit smaller pipework than the upstream line-in kit accepts
as this will impair performance.
Fig. 13
Step 1: twist
Step 2: unclip
Step 3: pull off
Fig. 14
Fig. 15
Fig. 16
Vessel Connector
Isolation Valve