Battery Testing

Testing your SPP1200 to determine its functional condition can 

be done in two ways.  The first is to test the open circuit voltage 

of the battery to determine the state of charge with a voltmeter.  

Testing Open Circuit Voltage means testing the battery’s voltage 

with nothing connected to the battery (disconnect one terminal).  

Consult the chart below to compare your readings:

Having the proper battery or amount of batteries for the system 

to be powered is extremely important to the life of the battery.  

When planning your power delivery system make sure you have 

the right amount of battery power so as to not discharge the bat-

tery too deeply during normal operation.  Even though the 

Stinger batteries have the best deep cycling ability in the market, 

the deeper the battery is cycled the shorter the life expectancy 

will be.  This is evident in the chart below:

Typical Stinger SPP1200 Cycling Ability 

vs. Depth of Discharge

Depth of Discharge

100%

50%
30%
10%

Typical Life Cycles

400
800

1450
4000

State of Charge vs. Open Circuit Voltage

Please  discuss  battery  selection  with  your  Stinger

®

  dealer 

prior to installation if you have any questions.

State of Charge

100%

75%
50%
25%

0%

Open Circuit Voltage

12.85 volts

12.5 volts
12.2 volts
11.9 volts
11.6 volts

Proper Battery Selection

The second way to test the battery is by using a load tester (usu-

ally available at your Stinger® dealer or most auto service cen-

ters).  A load test is performed on batteries that are suspect of 

having reduced output capacity.  For example a battery’s open 

circuit voltage tests good but the battery is unable to support a 

load.

Approximate Charging Times 

based on using a Current Tapering Charger set at

14.7 to 15 volts and 100% re-charge.

Automotive Current Tapering 

Charger Rated @:

SPP1200

10 amps

18 hours min.

22 hours max.

15 amps

15 hours min.

19 hours max.

20 amps

12 hours min.

16 hours max.

30 amps

9 hours min.

13 hours max.

40 amps

5 hours min.

10 hours max.

50 amps

5 hours min.

8 hours max.

Proper charging is crucial for proper performance of the 

SPP1200.  We recommend keeping the SPP1200’s voltage 

maintained at 12.8 volts (open circuit) by means of a properly 

designed regulated charging system.  If your battery has been 

discharged well below the recommended 12.8 volts we recom-

mend following chart to the right for proper recharging of the 

SPP1200.  The charging times stated are using an automotive 

Current Tapering Charger or otherwise know as a Constant 

Voltage Charger.  These chargers are microprocessor controlled 

and will regulate the charge voltage and current far better than 

the run of the mill automotive power charger.  Contact Stinger® 

for more information on how to obtain one of these superior char-

gers.

    Never use an inexpensive constant current or “trickle” charger!  

These chargers do not have regulated charging abilities.  They 

can overcharge the SPP1200 causing severe damage to the bat-

tery.  Even a small amount or .5 amp from a trickle charger if left 

on after the battery is fully charged will overcharge the battery.  

Overcharging will overheat and dry out the electrolyte causing 

the battery to fail prematurely.  Overcharged batteries are not 

covered under warranty.

    An undercharged battery not only has a temporary reduction in 

capacity, if left in an undercharged state or continually under-

charged, the capacity and life of the battery will be permanently 

reduced.  The battery warranty does not cover batteries that fail 

due to undercharging.  For this reason we recommend that you 

keep the battery fully charged at all times with a properly 

designed charging system that charges at 13.8 volts for float/

standby usage and 14.5-15 volts in cyclic applications.

Important Charging

 

Information

Specifications

Battery Design:

12 volt Dry Cell VRLA

Dimensions:

7.80” Wide

6.54” Deep

6.69” High

Weight:

33.29 lbs.

Internal Resistance:

<6 mOhms

Constant Discharge Capacity at 77o F10.50 Volts:

20 hour rate:

2.20A/44Ah

5 hour rate:

 7.48A/37.4Ah

½ hour rate:

55A/27.5Ah

Typical Cycle Life: 400 cycles @ 100% depth of discharge

(100% depth of discharge is down to 10.5 volts.  No lower!)

5 second Cranking Amps:

1200 Amps

CCA:

560 Amps

Maximum Charging 

Current

50 Amps

Any of the following actions will void the warranty!

Exposure of battery to gasoline or diesel fuel.

Removal of the battery’s top cover.

Removing or destroying the battery’s shipping date code.

Long Time Vehicle Storage

If you are going to store your vehicle for longer than 30 days you will 

need to take the following steps to prevent long term damage to the 

SPP1200.

1. Disconnect the battery from any and all power draining devices.

2. Do not leave a trickle charger on the battery.  This will overcharge 

the battery.

3. If you have components that need to stay powered during storage 

ie; car alarm system, you may use a battery tender device.  They 

have a regulated output that will monitor battery voltage closely and 

keep the battery at peak voltage.  Choose a tender that has the abil-

ity to reduce charge to .05 amps (five hundredths of an amp, not half 

an amp). 