© stilum GmbH, Gewerbegebiet Larsheck, D-56271 Kleinmaischeid • Tel. +49 (0) 2689 92790-0 • All rights and product modifications reserved.
Mounting instructions for „Pull over trainer“
Item-No. 55 1313 401
State: 28.01.2021 p. 2
1.
Select the fitness equipment location in consideration of the required movement
area (see diagram 3). Movement areas may overlap, exercise areas must not
be overlapped.
2.
Select the postition of the instruction sheet.
Attention:
Because of the risk of injury, the instruction sheet has to be arran
-
ged outside of the movement area.
3. Carry out excavation work for the foundation as shown in diagram 2.
After excavation compress the foundation floor.
Note:
Pay attention to items marked „ground level“ at the equipment!
4.
Carry out excavation work for the instruction sheet foundation as shown in dia
-
gram 4. After excavation compress the foundation floor.
5.
Set up the concrete foundations according to diagram 2 and 4 with central,
horizontal reinforcement.
6.
After a setting period of 10 – 14 days, depending on weather conditions and
foundation size, fill up and compress the holes between the foundation and the
foundation hole with excavation. Clean the foundation surface.
7.
Align the equipment and screw the base plates to the foundation using the
included heavy-duty dowels.
8.
Place the instruction sheet as well on the foundation and screw it onto the foun
-
dation with the included heavy-duty dowels.
NOTE:
We suggest to align the instruction sheet in such a way that the instruc
-
tions can be read while using the fitness equipment.
300
150
2551
1672
506
1100
1600
OHNE SCHRIFTLICHE ZUSTIMMUNG DER KAISER GMBH DARF DIESE
TECHNISCHE UNTERLAGE WEDER VERVIELFÄLTIGT, NOCH DRITTEN MITGETEILT ODER
ZUGÄNGLICH GEMACHT WERDEN, NOCH IN SONSTIGER WEISE MISSBRÄEUCHLICH VER-
WENDET WERDEN. ZUWIDERHANDLUNGEN WERDEN URHEBERRECHTLICH VERFOLGT.
1
Überzugtrainer
Benennung
Gepr.
Blatt
Datum
Projekt
Gez.
Zeichnungsnummer
1:20
A3
Name
Name
Fundamentplan
2003-00-00
Maßstab
Schramm
20.02.17
Gewerbegebiet Larsheck
56271 Kleinmaischeid
Deutschland
Beton
concrete
gewachsenes Erdreich
natural ground
Legende
stoßdämpfender Boden
shock-absorbing floor
ES
18.01.21
beliebiger Boden
A
Datum
Änderung
Rev
beliebiger Boden
optional floor
Diagram 2: Foundation plan
Reinforcement plan:
Concrete foundation with reinforcement
Foundation: BSt 500S
Stirrups Ø 8 mm lengthwise and cross
Concrete cover h´= 3 cm
Concrete quality class C20-25
ground level