CheCklist
www.stiebel-eltron.com
WPL A | WPL AC | WPL AS | WPL ACS |
5
EN
GL
ISH
This document is intended for qualified contractors.
Note
This checklist for commissioning is solely intended to provide assistance to contractors. It is not exhaustive and is subject to
change and correction. Contractors are responsible for the services and work they have provided and must observe and comply
with the latest technical standards and generally accepted engineering standards.
Note
Read the operating and installation instructions of the appliances and the accessories carefully before use and retain them for
future reference. The checklist cannot replace careful reading of the operating and installation instructions.
Checkpoint
Reference to the operat-
ing and installation in-
structions
Check-
box
Siting
Have the minimum clearances been maintained?
Heat pump: Chapter "Minimum
clearances"
Have the foundations been prepared in accordance with the in-
structions?
Heat pump: Chapter “Siting”
Can the condensate drain freely with no risk of frost?
Heat pump: Chapter "Conden-
sate drain"
Has the general information on sound and installation location
been taken into account?
Heat pump: Chapter "Prepara-
tions"
When installing on a wall mounting bracket: is the heat pump
standing on the anti-vibration mounts provided?
Wall mounting bracket WK 2:
Chapter "Securing the outdoor
unit"
Have the wall outlets for the hydraulic lines and electric cables
been sealed against moisture?
Hydraulic installation
Was the heating system flushed thoroughly with suitable water
before the heat pump was connected?
Heat pump: Chapter "Heating
water connection"
Have the flow and return been correctly connected to the heat
pump and indoor unit, cylinder or heating system, and protected
from frost with sufficient thermal insulation?
Heat pump: Chapters "Installing
the supply lines", "Flow and re-
turn connection"
If fan convectors are to provide cooling: Is the formation of con-
densate prevented on all lines that carry cold water?
Heat pump: Chapters "Buffer
cylinder", "Flow and return con-
nection"
Does the water quality correspond to the specifications of the
technical data table?
Heat pump: Chapter “Data
table”
Has the heating system been charged to the correct pressure?
Has the heating system been fully vented at the heat pump and
indoor unit, cylinder or elsewhere in the system and the air vent
valves then closed again?
Heat pump: Chapter "Venting
the heating system"
Indoor unit: See the relevant
chapter
For systems without a buffer cylinder: Have the specifications for
the minimum flow rate in the underfloor heating system been
safeguarded by having the heating circuits constantly open?
Heat pump: Chapter “Setting the
flow rate on the heating side”
For systems with a buffer cylinder: Has the flow rate on the heat-
ing side and heat pump side been set correctly?
Heat pump: Chapter "Setting the
flow rate on the heating side",
"Data table"
Has hydronic balancing been carried out?
CheCklist