19.2 Commissioning checklist
Note
This checklist for commissioning is solely intended to provide assistance to contractors. It is not exhaustive and is subject to
change and correction. Contractors are responsible for the services and work they have provided and must observe and comply
with the latest technical standards and generally accepted engineering standards.
Note
Read the operating and installation instructions of the appliances and the accessories carefully before use and retain them for
future reference. The checklist cannot replace careful reading of the operating and installation instructions.
Checkpoint
Reference to the operating and
installation instructions
Check-
box
Siting
Have the minimum clearances been maintained?
Heat pump: Chapter “Minimum clear-
ances”
Has the general information on sound and installation location been taken into
account?
Heat pump: Chapter “Preparations”
Have the wall outlets for the hydraulic lines and electric cables been sealed
against moisture?
Heat pump: Chapter “Wall outlet”
Hydraulic installation
Was the heat source system flushed thoroughly with brine before the heat pump
was connected?
Heat pump: Chapter “Installing the heat
source system”
Was the heating system flushed thoroughly with suitable water before the heat
pump was connected?
Heat pump: Chapter “Flow and return
connection”
Have the flow and return been correctly connected to the heat pump and the
cylinder or heating system and sufficiently insulated?
Heat pump: Chapter “Flow and return
connection”
Does the water quality correspond to the specifications of the technical data
table?
Heat pump: Chapter “Data table”
Has the heating system been charged to the correct pressure?
Has the heating system been fully vented at the heat pump and the cylinder or
heating system and the air vent valves then closed again?
Heat pump: Chapter “Filling the heating
system”
Have all the pipes in the heating system been sized correctly?
Has hydronic balancing been carried out?
Electrical installation
Have cables with a sufficient cross-section and the correct fuse protection been
used for the electrical connection?
Heat pump: “Data table”
Has the outside temperature sensor been installed on the correct side of the
building (north or north-east wall) and protected from external heating and
direct insolation?
Heat pump: Chapter “Sensor installa-
tion”
If cooling is to be provided: Have the room based remote controls been installed
in the lead room and connected electrically?
If cooling is to be provided: Has a buffer cylinder for cooling been installed and
connected in the heating system?
For systems with DHW heating: Have the DHW temperature sensors been prop-
erly connected, positioned and programmed at the programming unit?
Has the heating circuit flow sensor been correctly positioned and connected?
(lowest sensor well in the buffer cylinder)
Initial start-up
Has the correct language been set?
Programming unit: Operating instruc-
tions, chapter “Setting the language”
Has the set room temperature been selected?
Programming unit: Operating instruc-
tions, chapter “Adjusting the tempera-
ture (heating)”
Has the heating curve been set?
Programming unit: Operating instruc-
tions, chapter “Adjusting the tempera-
ture (heating)”
Has the buffer cylinder been configured correctly in the programming unit?
Programming unit: Commissioning
instructions, chapter “Controller menu”
(Settings / Buffer cylinder)
If cooling is to be provided: Has the heat pump for cooling been enabled and the
necessary settings made?
Programming unit: Commissioning
instructions, chapter “Controller menu”
(Settings / Cooling)