Installation, Operation and Maintenance (IOM) Manual
4.
Wiring Connections for Submersible Electric Motors
a.
Procedure of installation of submersible wires and cables for submersible electric motor shall
be in accordance to related electrical code & local regulations.
b.
Submersible wire or cable sizes must be appropriate to Kilowatt (kw) or Horsepower (hp)
rating of electric motor including voltage drop. Kindly refer to electrical code & local
regulations.
c.
Procedure of submersible wire or cable termination or connection should be followed in
accordance to electric code & local regulations. Please check IOM manual of submersible
motor for details.
d.
Electrical components related in protecting the electric motor against irregular conditions
should be installed in control panels.
SECTION VI. OPERATION PROCEDURE
1.
Pre-start-up & Checking
a.
Wear Personal Protective Gear or Equipment prior for start-up and operation.
b.
Prepare your instrument or tools to observe the performance of the pump.
c.
Check water source. Never operate the pump if water has presence of excess sand or any solid
particles.
d.
Check motor insulation using insulation tester. Never activate the motor if insulation reading
is less than 100 mega ohms. Please check IOM manual of submersible motor for details.
e.
Check power voltage. Never operate motor if voltage is not within the normal range. Please
refer Section VII. #5.a for reference.
e.
Make sure rotation of electric motor is correct prior for start-up to avoid producing strong
vibration during operation.
2.
Start-Up
a.
Close the isolation valve in discharge pipe.
b.
Start the driver.
c.
Slowly open the isolation valve in discharge pipe.
d.
Do not operate the pump exceeding to its rated working pressure.
e.
Use calibrated tester or current meter instrument to check if actual current of motor is within
the normal range.
f.
Observe the pump & discharge pipe. If excess vibration and disturbing noise are observe,
immediately shut down the motor and inspect the pump and main riser column pipe.
f.
Adjust all necessary protective electrical components in control panel for motor protection.
g.
Do not operate electric motors if actual voltage fluctuates. Please refer Section VII. #5.a for
reference.