8 | MRP Mobile Rotating Pulverizer Operation & Maintenance Manual
INSTALLATION
ATTACH TO EXCAVATOR
Use only approved rigging hardware rated for loads
greater than the weight of the attachment. Lifting
points are for moving the attachment only. Do not
lift other objects or use the attachment in a cable-
hung application.
1.
Locate flat, hard ground (e.g., concrete floor) for installation. Lift and place the attachment on the ground using the
lifting points. Use blocking if necessary.
2.
Ensure the attachment bracket is positioned vertically.
3.
Remove the excavator bucket. Follow the manufacturer’s recommended procedure.
Note: Plug hydraulic hoses to prevent contamination.
4. Clean the inside surface of the attachment bracket and all attachment pins. Remove all dirt and debris.
5.
Bring the excavator in position, carefully lining up the stick tip with the stick connection on the attachment bracket.
6. Pin the excavator stick to the stick connection.
7.
Carefully extend the excavator bucket cylinder to move the bucket linkage. Position the link into the attachment
bracket linkage connection.
8. Pin the linkage connection to the attachment bracket.
9.
Remove the transport pin.
Lifting Points
Connect to Stick