Furnace Dimensions
Figure 2
Furnace location
When finding a location to install the furnace, several things need to be kept in mind. Consider
the following things:
Service Access, Venting, Return air Duct, Supply air Duct and
Electrical.
Service Access.
The front panel is removable to allow access to the ash pan and the firebox for
regular maintenance. The Control Board is mounted on the left side. There are also 2 access
panels on the left side. The smaller cover gives access to the following components: Combustion
Fan, Vacuum Switch and Proof of Fire Switch. The larger cover allows access to the Convection
Blower for maintenance when needed. The Fan Limit Control is also located on the left side.
Supply Air.
The SC 050 Furnace may be connected to a gas, oil or Electric/Heat pump system
with existing duct work.
Return Air.
The furnace does not need to be connected directly
to the existing cold air return
system, but it is recommended.
Venting.
The location should be as close as possible to an outside wall for venting purposes. The
furnace requires 4” PL Vent pipe. The shortest vent system with minimal elbows is the best.