6 .  Commissioning and Maintenance

6 .1  Function check

The function of the HOLDX process guard locking has to be checked. Ensure the following 
before you start:
•  The process guard locking and the corresponding anchor plate are firmly seated.
•  The supply line is firmly seated and not damaged.
•  The system is free of all contamination.

Note

Damaged or defective devices must not be put into operation!

6 .2  Maintenance

The magnet coils are maintenance-free. If during the operation faults or failures of unknown 
origin occur, replace the magnetic guard lockings. Damaged or defective magnet coils or plug 
connectors must not be repaired and have to be replaced. If the magnet coils are exposed 
to excessive loads, additional safety measures may be necessary.

7 .  Disassembly and Disposal

7 .1  Removal

Disassembly of the process guard locking HOLDX L1 should only be performed in a de-en-
ergized state.

7 .2  Disposal

The process guard locking HOLDX L1 must be disposed of properly in accordance with 
national and local regulations.

8 .  Appendix

8 .1  Electrical connection

Note:

The illustrated examples are only suggestions. The user has the responsibility to 
design the overall system in compliance with applicable rules and regulations. 

Connection example 1: (individual wiring)

HOLDX L1

SAFIX S1

Connection example 2: Y-plug XCONN M12-Y

HOLDX L1

SAFIX S1

XCONN M12-Y

Summary of Contents for HOLDX L1

Page 1: ...LDX L1 7 10 Declaration of Conformity 8 10 1EC conformity regulations 8 1 About This Document 2 1 1 Function 2 1 2 Safety instruction for the authorized skilled personnel 2 1 3 Symbols 2 1 4 Scope of...

Page 2: ...n if the safety notes and instructions regarding assembly installation operation and maintenance are followed 1 6 Attention Incorrect use Danger to persons or damages to parts of machines or installat...

Page 3: ...be carried out by authorized skilled personnel The process guard locking can be installed on left or right hinged swing doors or sliding doors Install the guard locking and the anchor plate parallel...

Page 4: ...d must never be used to control a safety application 5 Diagnostic functions 5 1 Diagnostic function of the process guard locking The process guard locking HOLDX L1 indicates the operating condition as...

Page 5: ...x 3x pulsing Locking force of 900 N not reached 2 6 Locking force not reached 24 V 24 V not activated off on off 4x pulsing Magnetic flux interrupted when throw open the door 1 7 Error force measureme...

Page 6: ...magnet coils or plug connectors must not be repaired and have to be replaced If the magnet coils are exposed to excessive loads additional safety measures may be necessary 7 Disassembly and Disposal...

Page 7: ...x 6 slots M12 8 pin M23 connector plug for connection cable XCONN P6 M12 M23 SP X 71 000 01 Y distributor XCONN Y1 M12 SP X 71 000 02 Jumper plug M12 8 pin Connector plug for unused slots XCONN A1 SP...

Page 8: ...available at the SSP website www safety products de 10 Declaration of Conformity 10 1 EC conformity regulations SSP Safety System Products GmbH Co KG Max Planck Stra e 21 78549 Spaichingen 49 7424 98...

Reviews: