511-146P ROPE CLIMB 

INSTALLATION INSTRUCTION 

 

FOOTING INFORMATION 

 

Total footing depth is 24” less the height of the surfacing 
plus the height of the blocking material.  If you were using 
12” of surfacing the footing hole would need to be 12” plus 
the height of the blocking material (refer to the cutaway 
view to the right).   

 

If the Play structure is installed on an unlevel grade you 
must adjust the footing depth to accommodate the grade.  
For instance, if the grade for this component is 1” higher 
than the surface grade of the main playground post you 
must dig your footing hole 1” deeper. 

 

It is the owner/installers responsibility to check local 
building codes and to comply with those codes.  All footing 
depths listed here are recommendations and local soil types 
and frost lines may require a deeper and/or wider footing 
depth.  If that’s the case you must add more blocking 
material to accommodate the deeper footing, as the post 
length will still only be installed at the depth listed in this 
instruction manual. 

 

Assemble the entire unit before adding the concrete unless 
instructed to do so in the individual component instruction 
sections. 

 