Page 14 of 21
Installation & Adjustment Procedures
Figure 9: Typical Operating Pipe Arrangement
Figure 10: Typical Operating Arrangement
GENERAL INSTALATION NOTE:
When a switch uses an auxiliary switch arm, installation
will be easier if this pole is adjusted before installing the interphase pipe. This will eliminate
trying to coordinate and adjust all three poles at once.
GENERAL INSTALLATION NOTE:
If the components have self-piercing set screws, during
installation tighten them to only grip the pipe (match mark to check for slippage) and drive
them in only after adjustments are completed.
If a motor operator is used, at this point refer to its installation instructions for mounting,
checkout procedure, and trial operations.
Summary of Contents for CVB-2
Page 1: ...TYPE CVB 2 Vertical Break Disconnect Switch 15 5 245 kV 2000A INSTRUCTION INSTALLATION MANUAL ...
Page 2: ...Page II The Quality Name in High Voltage Switching ...
Page 3: ...Page III The Quality Name in High Voltage Switching Safety Information ...
Page 7: ...Page VII The Quality Name in High Voltage Switching Type CVB 2 ...
Page 31: ......