18 • Starting Procedure
________________________________________________________________________________________________
8.
STARTING PROCEDURE
1
When mains voltage is connected to the RVS-AX, even if start signal has
not been issued, full voltage may appear on the starter load terminals.
Therefore, for isolation purposes, it is necessary to connect an isolating
device before (upstream) the starter.
2
Power factor correction capacitors must not be installed on starters load
side. When required, install capacitors on starter’s line side.
3
Before starting the motor verify its rotation direction. If needed,
disconnect the rotor from the mechanical load and verify the right rotation
direction.
4
Prior to Start up procedure make sure that line voltage match the one
shown on the starter’s name plate.
5
Do not interchange line and load connections
6
Do not connect the RVS-AX “Inside delta”. (Consult factory)