SURFACE MOUNT (SIDE WALL) INSTALLATION
NOTE:
Locate the power vent termination following the clearance to combustible table, venting
configuration diagram (Fig. #2 & 3), and terminal location diagram (Fig. #1).
NOTE:
The following instructions are for use SCPV-459SM & SCPV-459SM-10 only.
1.
SCPV-459SM and SCPV-459SM-10 are designed to fit on center in between standard exterior 2x6
exterior framing. The opening required in the framing and exterior sheathing is 14.50” (368mm)
wide by 10.00” (254mm) tall as shown in the image (right).
2.
The power vent termination is secured to the sidewall by the left and right nailing flanges shown
on page 7.
3.
The power vent termination requires a 1/8” clearance to the siding to permit servicing of the
blower motor. The opening required in the siding is 11.50” (292mm) wide by 10.25” (260mm) tall.
Required opening in framing & sheathing
Power Vent installed in required
opening in framing & sheathing
Required opening in finished siding
Power Vent install with finished siding