6 Installation
6.9 Fill the heating system
The filling can be done via the drain connection
of
the boiler. This is placed on the back of the heat
exchanger.
6.10 Bleed the heating system
Boilers of the series
maxi
mus
have no vent valves
installed in the boiler. The venting takes place via the
piping system (e.g. vent valve in the boiler safety
group). Set venting option at the highest point of the
entire system in the flow.
6.11 Establish the chimney connection
See instructions for execution
6.11.1 Flue gas pipe: Hole for emission mea-
surement
►
Make the hole for the emission measurement
according to the following images (recom-
mendation according to standard).
►
If these specifications cannot be implemented,
then make the measuring point after a calming
section, i.e. after the longest straight section of
the pipe. The tube orientation (horizontal, vertical,
oblique) plays no role in this case.
►
In any case, place the measuring point before any
existing draught limiters.
You can find the function for carrying out the emission
measurement in the boiler operation manual, keyword:
Chimney sweep function.
Exhaust pipe horizontal
Exhaust pipe vertical
6.12 Mount ash container
Fig. 2-34: Mount ash container
22