Perform this step when the modules are exposed to sunlight. If the string length is
changed or a power optimizer is replaced, repeat the pairing process.
1. From the
Commissioning
menu, select
Pairing
.
2. Tap
Start Pairing
.
3. When Pairing Complete is displayed, the system startup process begins:
Since the inverter is ON, the power optimizers start producing power and the
inverter starts converting AC.
WARNING!
When you turn ON the inverter ON/OFF/P switch, the DC cables carry a high
voltage and the power optimizers no longer output a safe output.
When the inverter starts converting power after the initial connection to the AC, the
inverter enters Wake up mode until its working voltage is reached. This mode is
indicated by the flickering green inverter LED.
When working voltage is reached, the inverter enters Production mode and
produces power. The steadily lit green inverter LED indicates this mode.
4. Tap
OK
to return to the
Commissioning
menu.
Communication
Communication settings can be configured only after communication connections are
complete. Refer to
Setting Up Communication with the Monitoring Platform on page 47.
Select
Monitoring Communication
to configure communication with the
monitoring platform.
Select
Site Communication
to configure communication between multiple
SolarEdge devices or external non-SolarEdge devices, such as batteries or loggers.
StorEdge Three Phase Inverter MAN-01-00648-1.3
43
Step 2: Commissioning and Configuring the Installation