HEAT PUMP AND TANK ASSEMBLY
22
ASSEMBLY PROCEDURE
Warning:
The heat pump must be assembled, plumbed and filled with water prior to power being
connected and switched on.
The following procedure should be followed to properly lift, place and connect the heat pump module onto
the storage tank:
1.
Storage Tank:
Remove all packaging including the carton base from the storage tank and position in its
intended location, supported by a level slab or solid base.
The water connections are on the left hand side and should be parallel to the wall, unless the water
heater is to be installed in a manifolded bank of water heaters. If the water heater is installed in a
manifolded bank of water heaters, refer to
“Multiple Installations”
on page 32 for information on the
correct storage tank orientation.
The storage tank is to be positioned at least 100 mm from the wall and such that when the heat pump
module is in position on top of the storage tank, there is a clearance of 300 mm perpendicular from both
the air inlet and outlet louvres to any wall or obstruction.
Ensure the power cable and tank sensor cable are hanging down the side of and not sitting on top
of the storage tank before lifting the heat pump module into position.
HEAT PUMP DIMENSIONS
Step 1
position storage tank at least 100 mm from the wall
and allow for at least 300 mm ventilation clearance
2.
Heat Pump Module:
Place the heat pump module in front of the storage tank and open the top flaps of
the carton.
Two (2) lifting bars are housed in a recess in the cardboard layer on top of the heat pump module.
Remove the lifting bars and set them aside.
Remove the carton from the heat pump module.
Be aware the carton sides have flaps, which tuck under the carton base of the heat pump module.