7 Equipment use
Preliminary
The equipment is studied for the demolition of:
•
Non-reinforced structures
•
Reinforced concrete e cutting of rebars
The structures to be demolished must not danger through the presence of liquids or gas in
pressure, corrosives or instable, without electricity, without the structure tensioned with high
resistant cables.
The operator must verify that the above are not present on the worksite.
Other operations of demolition/crushing non specified in this manual must be planned by the
jobsite manager.
Your attention is required for the following points:
-
The equipment must be used only by qualified personeel who has read this manual, who is
authorized to use the equipment and has experience in use and functioning of the
equipment. Toread this manual periodicallu is suggested.
-
The operator’s knowledge of the control devises is fundamentalin order to use the
excavator and the equipment.
-
Avoid any type of work that can mean non-staqbility of the excavator or the assembly of the
excavator-equipment.
Materials to be worked on
Please see the table 1 for the largest dimensions of the masses, instead regarding the materials to
be worked please see the following limitations:
-The equipment can be used to demolish reinforced concrete or prestressed concrete, with a cubic
resistance of RBK<55N/mm2. It can be also used for materials such as natural stone, cement
bricks or similur, having a resistance below value here specificed.
-The bladesm of the crusher can be used to cut iron rebars, alluminium and copper bonds having a
max load of below 750 N/mm2 and hardness below 230HB.
Usage
In order to carry out these operations the operator must:
-position the excavator near the mas to be worked on;
-the operation of crushing the masses in reinforced concrete produces the launching the materials
on all the area below the material being crushed, for a radius of serverl meters, area which must
be cleared from materials or other things that can get damaged;
-the operation of cutting metallic masses determines the falling of heavy pieces and the launching
of smaill parts, on all the area below the mass, for a radius of serveral meters, area that must be
cleared from materials or other things that can get damaged;
-position the crusher in such a way that the material is palced between the jaws, taking care that
the jaws are perpendicular to the side of the material, in order to avoid actions that can damage
the crusher movments;
-proceed in closing the jaws with care, verifing that the crushing and or the cutting operation is
proceeding in way regular way, without producing large pieces closed between the jaws;
EQUIPMENT USE
12
Page
of 29
7
Summary of Contents for PDO 100
Page 4: ...Page 4 REQUEST OF SPARE PARTS 29 16 Richiesta parti di ricambio of 29 ...
Page 21: ...14 15 16 17 5 3 8 9 4 1 7 12 10 2 11 13 6 COMPLETE PDO PARTS DRAWINGS 21 Page of 29 12 ...
Page 25: ...41 46 46 41 43 44 45 47 42 41 50 49 48 COMPLETE CYLINDER 25 Page of 29 14 ...
Page 27: ...55 54 53 54 58 59 52 57 56 51 60 COMPLETE DISTRIBUTOR 27 Page of 29 15 ...