Chapter 5 : Menus
UPS/NTA GB/ DELMX_EXPC1C3C6.B
page 32
12.4. Battery
The battery test is for controlling the battery capacity to supply energy. The battery test can either
be made manually or automatically.
12.4.1. Battery test information
This menu provides information to show:
- the result of the latest battery test (OK or faulty),
- date and time of the latest battery test,
- date and time of the next battery test.
12.4.2. Conditions to start the battery test
The battery test can only be started if the following conditions are fulfilled :
- rectifier operating
- no overload on inverter
- bypass available
- battery circuit closed
- no rectifier mains outage for at least 48 hours.
12.4.3. Test programming
The battery test can be made automatic from the control panel by setting the frequency, the
day of the week and the time.
Title screen / battery / battery test programming
BATTERY : BATTERY TEST PROGRAMMING
BATTERY TEST:
inactive
PROGRAMMED ON: Friday at 20:00
EVERY:
8
days ?
12.4.4. Starting the manual test
The test conditions being fulfilled, the manual test can be started by entering the menu
"
BATTERY / BATT MANUAL TEST
".