Installation manual of KTS-O-(E)S type fire dampers in building barrier

Version: 3.1 

 

b)

 

Horizontal barrier (ceiling) 
 

Variant I (without using pos. 1 ÷ 5) 
- permissible only when the fire damper mechanism is above the ceiling, figure 3. 

1.

 

Make an opening in the wall with the minimal size DN+70 [mm] 

2.

 

Put the fire damper into the installation opening to the depth of flange. The fire 
damper should be suspended or supported it in such way that axis of the fire damper 
should coincide with the axis of the installation opening (coaxiality). 

3.

 

After setting the fire damper in accordance to the guidelines, fill the gap between 
the fire damper and the ceiling with cement and lime mortar or concrete. In place of 
cement and lime mortar and concrete, the fire protective mortar e.g. PROMASTOP 
MG III made by PROMAT may be used. 

4.

 

After drying of the mortar, remove used supports and suspensions which were used 
during installation of the fire damper. 

 
 
Variant II – Recommended by SMAY company  

1.

 

Make an opening in the ceiling with the minimal size DN+70 [mm] 

2.

 

Install the mounting plate pos.  1 to the fire damper using M6 screws pos. 2,3,4. 
Depending on the fire damper position – the drive mechanism will be located under 
the ceiling (Figure 2) or above the ceiling (Figure 3), mounting plate pos. 1 will be 
installed in front or behind the flange of the fire damper in accordance with the 
detail A or B. 

3.

 

Make holes for the rawlbolts pos. 5 according to the drawing. 

4.

 

Put the fire damper into the installation opening to the depth of flange in the way 
that axis of the fire damper should coincide with the axis of the installation opening 
(coaxiality) and screw it by means of rawlbolts pos. 5. 

5.

 

After setting the fire damper in accordance to the guidelines, fill the gap between 
the fire damper

 

and the ceiling with cement and lime mortar or concrete. In place of 

cement and lime mortar and concrete,

 

the fire protective mortar e.g. PROMASTOP 

MG III made by Promat can be used. 

 

 

Summary of Contents for KTS-O-E

Page 1: ......

Page 2: ...n conditions sensitivity Closing opening in appropriate moment and acceptable time pass Response time closing time pass Operational reliability KTS O E 10 000 cycles pass KTS O S 300 cycles pass Fire resistance Integrity E Insulation I Smoke leakage S Mechanical stability EI 120 ve ho i o S under E Maintenance of the cross section under E Durability Of response delay pass Of operational reliabilit...

Page 3: ...of flange The fire damper should be suspended or supported it in such way that axis of the fire damper should coincide with the axis of the installation opening coaxiality 3 After setting the fire damper in accordance to the guidelines fill the gap between the fire damper and the wall with cement and lime mortar or concrete In place of cement and lime mortar and concrete the fire protective mortar...

Page 4: ...page 4 z 9 Installation manual of KTS O E S type fire dampers in building barrier Version 3 1 Figure 1 Installation method of fire damper KTS in rigid barrier wall ...

Page 5: ...ctwork suspensions have to provide full load capacity 4 Ductwork suspensions fixed to the fire damper have to be made in accordance with the ductwork manufacturer instructions The KTS O E S fire dampers may be installed also in horizontal barriers thicker than the length of the damper body In such case ventilation duct would be partially inbuilt in the fire barrier KWP built in inside the barrier ...

Page 6: ...pensions which were used during installation of the fire damper Variant II Recommended by SMAY company 1 Make an opening in the ceiling with the minimal size DN 70 mm 2 Install the mounting plate pos 1 to the fire damper using M6 screws pos 2 3 4 Depending on the fire damper position the drive mechanism will be located under the ceiling Figure 2 or above the ceiling Figure 3 mounting plate pos 1 w...

Page 7: ...page 7 z 9 Installation manual of KTS O E S type fire dampers in building barrier Version 3 1 Figure 3 Installation method of fire damper KTS in rigid barrier ceiling ...

Page 8: ...page 8 z 9 Installation manual of KTS O E S type fire dampers in building barrier Version 3 1 Figure 4 Installation method of fire damper KTS in rigid barrier ceiling ...

Page 9: ...ire dampers in building barrier Version 3 1 Mounting plates pos 1 may be made to size and provided by SMAY L L C company or made by the customer in accordance with drawing and instruction Figure 5 Mounting plate pos 1 Detail A Detail B Figure 6 Details ...