MGC300 Genset Controller User Manual
MGC300 Genset Controller Version 1.1 2020-01-04 Page 23 of 27
10
COMMISSIONING
Before official operation, the following checks are suggested to do:
a) Check all the connections are correct and wire diameter is proper.
b) Make sure that the controller DC power has fuse, and it is correctly connected to the positive and
negative of start battery.
c) Take proper action to prevent engine from cranking successfully (e. g. remove the connection wire of
gas valve). Make sure everything is correct. Connect starter battery power, and the controller shall
conduct the procedure;
d) P
ress “Start” button, and genset will start. After the set cranking times, controller will send signal of
Start Failure; and then pr
ess “Stop” to reset controller.
e) Recover the action of preventing engine from cranking successfully (e. g. recover the wire of gas
valve). Press Start button again, and genset will start. If everything goes well, genset will go normally
running after idle running (if configured), and Mains and Gen will close. During this period, please
observe
engine’s running state, AC generator’s voltage and frequency carefully. If there is something
unusual, stop the running genset and check all wire connections according to this manual.
f) For any other questions please contact with SmartGen service personnel.