SMA CLUSTER CONTROLLER User Manual Download Page 83

15.5 Setting SMA Grid Guard Mode

When the inverters are delivered, the SMA Grid Guard parameters have a default setting
depending on the country. Changes to the SMA Grid Guard parameters must always be agreed
upon with the grid operator and are recorded in the event logs of the inverters. To change
SMA Grid Guard parameters, the SMA Grid Guard mode must be activated on the
Cluster Controller user interface. For this purpose, you require a personal SMA Grid Guard code.
You can request your personal SMA Grid Guard code from SMA Solar Technology AG
(application for the SMA Grid Guard code available at www.SMA-Solar.com).

Requirements:

☐ The responsible grid operator must approve changes to grid-relevant parameters.
☐ The SMA Grid Guard code for changing the grid-relevant parameters must be available

(application for the SMA Grid Guard code available at www.SMA-Solar.com).

Procedure:

1. Log into the Cluster Controller as 

Installer

.

2. Select the SMA Grid Guard symbol (

) in the status bar.

☑ The SMA Grid Guard dialog window opens.

3. Set the SMA Grid Guard mode:

• To activate the SMA Grid Guard mode, enter the personal SMA Grid Guard code in

field 

Individual access code

.

• To deactivate the SMA Grid Guard mode, enter the blocking code 

54321

 in field

Individual access code

.

4. Select [

OK

].

☑ The SMA Grid Guard mode is set. In the system tree, updating the symbols for access rights

(SMA Grid Guard symbol and padlock symbol) can take up to two minutes.

15 Passwords and SMA Grid Guard

SMA Solar Technology AG

User Manual

83

ClusterController-BA-en-15

Summary of Contents for CLUSTER CONTROLLER

Page 1: ...User Manual SMA CLUSTER CONTROLLER ClusterController BA en 15 Version 1 5 ENGLISH...

Page 2: ...ntified as such A lack of identification does not mean that a product or symbol is not trademarked The BLUETOOTH word mark and logos are registered trademarks of Bluetooth SIG Inc and any use of these...

Page 3: ...1 Functions 12 3 1 2 Type Label 17 3 1 3 LEDs 18 3 1 4 Display 19 3 1 5 Keypad 20 3 2 Sunny Portal 21 4 User Interface of the Cluster Controller 22 4 1 User Groups and User Rights 22 4 2 Overview of...

Page 4: ...Synchronizing System Time via the Internet 38 6 7 3 Manually Setting the System Time 39 7 Device Configuration 40 7 1 Setting the Characteristic Curve of the Irradiation Sensor 40 7 2 Parameter Setti...

Page 5: ...ng Off the Type Serial Number and Firmware Version of the Devices 53 10 4 IP Addresses of the Devices 54 10 4 1 Reading Off the IP Address of the Cluster Controller 54 10 4 2 Reading Off the IP Addres...

Page 6: ...roller 73 14 1 2 Setting the Automatic Update for Connected SMA Devices 73 14 2 Manual Update 75 14 2 1 Carrying Out a Manual Update for Cluster Controller 75 14 2 2 Performing a Manual Update for Con...

Page 7: ...8 1 LED States 90 18 1 1 Operation LEDs 90 18 1 2 Network Port LEDs 95 18 2 Errors in the Cluster Controller or the Connected Devices 96 18 3 Restarting the Cluster Controller via the User Interface 1...

Page 8: ...rectives Knowledge of and compliance with this document and all safety information 1 3 Additional Information Links to additional information can be found at www SMA Solar com Document title Document...

Page 9: ...Settings Enter 10 in the field Minutes Connects several elements to be selected Select Settings Date Button Key Button or key to be selected or pressed Select Next 1 6 Nomenclature Complete designatio...

Page 10: ...ther than that described in the Intended Use section does not qualify as appropriate The enclosed documentation is an integral part of this product Keep the documentation in a convenient place for fut...

Page 11: ...mber of connected inverters the frequency of device updates the frequency of data transfer to Sunny Portal and the use of FTP push SMA Solar Technology AG recommends using an Internet flat rate 2 4 Sy...

Page 12: ...e system Implementation and feedback of grid operator setpoints for active power limitation and reactive power operation under grid management services Implementation and feedback of setpoints for act...

Page 13: ...and reactive power operation under grid management services With the Cluster Controller as part of grid management services you can implement different grid operator setpoints for active power limitat...

Page 14: ...strongly limits the active power of the system Sending the system data to an FTP server and or the Sunny Portal Internet portal The Cluster Controller can automatically send the system data that has b...

Page 15: ...esignation A PV Modules B Module temperature sensor C Inverter D Outside temperature sensor E Irradiation sensor F Cluster Controller G Sunny Portal H Router I Ripple control receiver or remote termin...

Page 16: ...ntrol example Position Designation A PV Modules B Module temperature sensor C Inverter D Outside temperature sensor E Irradiation sensor F Cluster Controller G Industrial load H Sunny Portal I Router...

Page 17: ...ng customer support from Service see Section 20 Contact page 111 Symbols on the Type Label Symbol Designation Explanation C Tick The product complies with the require ments of the applicable Australia...

Page 18: ...con nected devices as well as the communication status of the system and the status of the grid management services see Section 18 1 LED States page 90 Data carrier status LED Shows the status of the...

Page 19: ...figured The display languages are German and English You can change the display language via the Cluster Controller user interface Figure 5 Cluster Controller display example Position Designation Expl...

Page 20: ...digital inputs are summarized in two groups here Meteorology Displays the measured values of the connected irradiation sensor and the connected temperature sensors Active power limitation Displays th...

Page 21: ...Storage System In addition data from battery management systems such as Sunny Island and Sunny Boy Smart Energy can be displayed in clearly arranged diagrams In order to use Sunny Portal you will need...

Page 22: ...age 88 or the NAT port see Section 17 5 page 88 Reading off the inverter power and the inverter parame ter settings via the device menu see Section 4 2 4 page 26 Setting the inverter parameters see Se...

Page 23: ...cess to the main functions of the Cluster Controller B System tree Presents all devices in the system in a tree structure C Device menu Provides various device information and configuration options fo...

Page 24: ...is activated see Section 14 1 1 page 73 and a new firmware version is available the new firmware version is displayed in brackets after the current firmware version 4 2 2 Toolbar Symbol Designation E...

Page 25: ...e serial number of the device is dis played as the default device name You can change the device name see Section 10 1 page 53 Status symbols in the system tree Symbol Designation Explanation Neutral...

Page 26: ...enu 4 2 4 1 Overview Menu Depending on whether you have selected the system view or the device view in the system tree the menu Overview displays the most important information on the overall system o...

Page 27: ...ameters of the selected system or of the device selected in the system tree The parameters that are displayed depend on the user group and the selected device All parameters are summarized in expandab...

Page 28: ...ion or the reactive power setpoint The menu Grid management services is only displayed if the Cluster Controller is selected in the system tree Configurable parameters for digital and analog inputs Pa...

Page 29: ...e setpoint of the displacement power factor cos For setpoint cos Phi Cos Phi end setpoint Upper limit for the setpoint of the displacement power factor cos For setpoint cos Phi Excitation type Directi...

Page 30: ...mmand with the new output value is to be sent to the inverters once the set point sent by the signal generator changes The first output value is sent to the inverter immediately after the setpoint is...

Page 31: ...me and could not yet be remedied Incoming error An Error event has occurred Outgoing error The Error event no longer exists Warning The Warning event has existed for some time and could not yet be aut...

Page 32: ...roups depend on the devices available in the system or the device selected in the system tree Symbol Designation Explanation Status General information on device status Type label All values that iden...

Page 33: ...for grid feed in at the medium voltage level These parameters are protected by the personal SMA Grid Guard code Grid connection Definition of measurement source for system ac tive power at the grid c...

Page 34: ...currently being saved in the device Average value Displays the average value Total Displays aggregated values Maximum Displays the maximum value Minimum Displays the minimum value Update Indicates th...

Page 35: ...group User group Default system password User 0000 Installer 1111 If you have not yet changed the default system password of your user group you should change the default system password of both user...

Page 36: ...language will be English 6 1 2 Adjusting the Display Contrast 1 Call up the display view Settings To do this simultaneously press and hold the OK and ESC buttons on the keypad for two seconds The dis...

Page 37: ...user interface and the Cluster Controller display The format change has no effect on data exports Procedure 1 Select the Cluster Controller in the system tree and select the menu Settings in the devi...

Page 38: ...ing system time If you change the system time the inverters will adopt the new system time immediately Additional communication products in the system do not adopt the system time for some time but a...

Page 39: ...r the NTP server once a day at around 9 p m 10 To trigger time synchronization manually select the button Execute in the field Trigger time synchronization For manual time synchronization the Cluster...

Page 40: ...nsor see manual from manufacturer 5 Select Save 7 2 Parameter Settings 7 2 1 Setting Parameters for a Device Class A device class refers to all devices of the same type You can configure all the devic...

Page 41: ...splayed on the user interface of the Cluster Controller via an hourglass symbol and may take several hours if the DC input voltage in the inverter is too low e g at night 7 3 Deactivating the Webconne...

Page 42: ...tion 1 Select the Cluster Controller in the system tree and select the menu Update and save in the device menu 2 Select the parameter group Device configuration and select Save device configuration 3...

Page 43: ...figuration file is displayed in the field Restore device configuration bak 5 Select Execute The configuration file is uploaded and the device configuration is restored The Cluster Controller restarts...

Page 44: ...can access the exported system data directly via the inte grated FTP server The integrated FTP server is protected via the system password of the respective user group Export to external FTP server T...

Page 45: ...for each day and saves the collected system data to this directory every five minutes as XML files Every 15 minutes the XML files are packaged to a ZIP file containing three XML files Directory path a...

Page 46: ...ndividual values are separated by a colon Example D Key SENS0700 5141 TmpMdul C Key Min Minimum value in the measurement interval calculated by all devices con nected to the Cluster Controller Max Max...

Page 47: ...r to display the measured values as a term In the drop down list Measured value name in local language select No in order to display the technical name of the measured values 5 Select Save 8 4 Exporti...

Page 48: ...st Data export in XML format 5 Select Save 8 5 2 Activating or Deactivating the Integrated FTP Server 1 Select the Cluster Controller in the system tree and select the menu Settings in the device menu...

Page 49: ...al FTP server For FTP Push port 21 is set by default The collected system data is uploaded to the given directory and in the selected data format every 15 minutes Requirements Port 21 must be approved...

Page 50: ...u Settings in the device menu 2 Select the parameter group Further Applications FTP Push 3 Select Edit 4 Deactivate the export of system data In the field Data export in CSV format select the entry No...

Page 51: ...to the Cluster Controller as Installer 2 Select the Cluster Controller in the system tree and select the menu Settings in the device menu 3 Make the settings for the SMTP server Select the parameter g...

Page 52: ...ctive power limitation 6 Select Save 7 Test the alarm via e mail Select the group E mail In the field Send test e mail select Execute The Cluster Controller sends a test e mail to the given e mail add...

Page 53: ...ber can be found on the type label of the Energy Meter Procedure 1 Select the Cluster Controller in the system tree and select the menu Settings in the device menu 2 Select the parameter group system...

Page 54: ...e menu 2 Select the parameter group External communication and read off the IP address If the Cluster Controller automatically receives its IP address via DHCP read off the IP address in the group DHC...

Page 55: ...d see Section 15 3 page 80 4 If you are using Sunny Portal activate the inverter in Sunny Portal see the user manual of the Cluster Controller in Sunny Portal 10 6 Replacing the Cluster Controller or...

Page 56: ...lect the entry Yes in the drop down list Use Sunny Portal 6 Make the user settings in the group User settings In the field E mail enter the e mail address to which Sunny Portal is to send the access d...

Page 57: ...ery 8 hours is selected in the Cluster Controller for sending the communication monitoring signal and the communication monitoring setting Sharp is selected in Sunny Portal If Sunny Portal has not rec...

Page 58: ...ter Controller in the system tree and select the menu Settings in the device menu 2 Select the parameter group Sunny Portal Basic settings 3 Select Edit 4 In the drop down list Upload frequency select...

Page 59: ...y WebBox in the Sunny Portal system where you wish to integrate the Cluster Controller delete the Sunny WebBox from the Sunny Portal system see user manual of the Cluster Controller in Sunny Portal 3...

Page 60: ...default setting 502 7 Select Save 8 If required make additional Modbus settings see the Technical Description SMA CLUSTER CONTROLLER Modbus Interface 12 2 Saving or Updating the Modbus Profile and Sy...

Page 61: ...ter group Modbus 3 To save the automatically created system configuration select Save automatically generated system configuration sysplant xml 4 To save the user defined system configuration file sel...

Page 62: ...gnal source The different signal sources can be combined Type of setpoint signal Explanation Digital signals The setpoints are transmitted to the Cluster Controller as digital signals in the form of b...

Page 63: ...ect the menu Settings in the device menu 6 Select the parameter group System device control 7 Select Edit 8 To enable the inverters to receive and implement setpoints for active power limitation from...

Page 64: ...power By default the nominal inverter power available in the system is used as the value for total system power In the drop down list Total system power select the entry User defined In the field Sav...

Page 65: ...es at intervals of 60 seconds Once the modified setpoint has been reached the Cluster Controller once again sends the current output value at the time interval you entered for the parameter Time inter...

Page 66: ...Grid Guard dialog 3 In the field Individual access code enter the personal SMA Grid Guard code 4 Select OK The SMA Grid Guard mode is activated In the system tree updating the symbols for access right...

Page 67: ...ctive power limitation must be agreed upon with the responsible grid operator The necessary parameter for the active power limitation must be set in the inverter see Section 13 2 page 63 Procedure 1 L...

Page 68: ...ce menu 3 Make the general settings Select the parameter group General settings System control Select Edit In the drop down list Operating mode select the entry Open loop control If you are using digi...

Page 69: ...nt and the voltage is used as setpoint Input signals up to 21 mA possible For an analog signal source the Cluster Controller classifies input signals as valid up to a maximum of 21 mA This enables int...

Page 70: ...elect the group Status configuration The columns cos Phi and Excitation type are also displayed Depending on the number of digital inputs used in the column Active activate the selection field of the...

Page 71: ...s 4 Select Edit 5 Make the desired settings for the fallback In the drop down list Fallback activated select the entry Yes In the field Fallback activates after enter the desired time after which the...

Page 72: ...5 Select the group Configuration of system control via communication 6 To set the fallback for reactive power setpoint to the setpoint cos Phi select the group cos Phi specified by PV system control 7...

Page 73: ...in the device menu 2 Select the parameter group Device Update 3 Select Edit 4 Select the desired entry in the drop down list Automatic update Entry Explanation Yes Activates the automatic update No De...

Page 74: ...ect the entry No in the drop down list Activated 5 To activate the automatic update make the following settings In the drop down list Activated select the entry Yes default setting In the drop down li...

Page 75: ...whether a new update is available If a new update is available the Cluster Controller downloads the update from the SMA Update Portal and starts the update process Performing a Manual Update via the U...

Page 76: ...input voltage Depending on the time of day the weather or the condition of the PV modules e g affected by pollution or covered with snow the DC input voltage may be too low for the update The affected...

Page 77: ...com 2 Log into the Cluster Controller as Installer 3 In the system tree select the system and select the menu Updates in the device menu 4 Select the parameter group Update 5 In the field Upload upda...

Page 78: ...completed successfully 4 Remove the USB data carrier from the Cluster Controller 5 Select Send The Cluster Controller checks the saved files The Cluster Controller sends the update file once a day on...

Page 79: ...ords that have any personal relevance to you such as the names of persons or pets personnel numbers identification numbers or car license plates Do not repeat names or words e g househouse or catcat D...

Page 80: ...g into the Cluster Controller as Installer 2 Select the Cluster Controller in the system tree and select the menu Settings in the device menu 3 Adapt the system password to the device password Select...

Page 81: ...there is one PUK for each user group User and Installer Procedure 1 Download the PUK application form application form available at www SMA Solar com 2 Complete the application form and sign it 3 Sen...

Page 82: ...rd In the field Confirm password enter the new system password again Select Save The Cluster Controller changes the system password for the user group Installer and the inverter is no longer displayed...

Page 83: ...must approve changes to grid relevant parameters The SMA Grid Guard code for changing the grid relevant parameters must be available application for the SMA Grid Guard code available at www SMA Solar...

Page 84: ...y default Procedure In Sunny Portal select the Cluster Controller on the page Configuration Device overview The login page of the Cluster Controller opens Access via WAN IP Address Requirement Corresp...

Page 85: ...2 Set up the router for DynDNS see router manual 3 Set up corresponding port forwarding in the router see router manual The Cluster Controller is set to HTTP port 80 and NAT port 80 by default 16 Sett...

Page 86: ...on how to configure the router or network switch see the manual from the manufacturer Procedure 1 Write down the previous IP address subnet mask and gateway address of the computer 2 Connect the compu...

Page 87: ...Procedure 1 Log into the Cluster Controller 2 Select the desired inverter in the system tree 3 Select the menu Settings System communication in the device menu 4 Select Edit 5 In the drop down list Au...

Page 88: ...er Controller you must specify this changed HTTP port together with the IP address of the Cluster Controller when calling up the user interface Example Calling up the user interface of the Cluster Con...

Page 89: ...3 Select Edit 4 In the field Port enter the desired port default setting port 80 5 Select Save 17 Network Configuration SMA Solar Technology AG User Manual 89 ClusterController BA en 15...

Page 90: ...Connect the Cluster Controller to the voltage supply see the Cluster Controller installation manual The voltage supply is reverse connected or the power supply unit is defective Corrective measures En...

Page 91: ...mmunication with at least one device is dis turbed The Cluster Controller may not be con nected to the device Corrective measures Ensure that the network cables are correctly connected see the Cluster...

Page 92: ...es is disturbed There is a problem in the LAN Corrective measures Ensure that the network cables are correctly connected see the Cluster Controller installation manual Check whether the network compon...

Page 93: ...ntroller event log see Section 9 1 page 51 If the SD memory card is defective contact the Service see Section 20 page 111 flashing red The Cluster Controller could not start correctly A system error h...

Page 94: ...10 glowing yellow The USB data carrier connected to USB port 1 is compatible but the free storage capacity is no more than 10 Corrective measures Delete files that are no longer required from the USB...

Page 95: ...measures Ensure that the network cables are correctly connected see the Cluster Controller installation manual No network connection established One or more network components network cables or con ne...

Page 96: ...s Ensure that the voltage supply is correctly connected see the Cluster Controller installation manual If the voltage supply is connected correctly replace the power supply unit User Interface and Dis...

Page 97: ...e Speedwire Webconnect interface Ensure that the network cable of the inverter connected directly to the Cluster Controller is connected to network port X9 or X10 of the Cluster Controller Ensure that...

Page 98: ...connected a mea sured value of up to 2 2 V for pin group Analog voltage input 4 is shown on the display and the user in terface If no sensor is connected to the pin group Analog volt age input 4 a me...

Page 99: ...ge supply is connected correctly replace the power supply unit A firewall is blocking the connection Corrective measures Adjust the firewall settings in order to allow the required connection If the C...

Page 100: ...e problem persists contact the network administrator The login page does not open If the Cluster Controller is accessed via the Internet there may not currently be an Internet connection or the port f...

Page 101: ...splayed next to the event type This event can only be rectified by SMA Service Corrective measures Contact the user with Installer rights and inform them of the serial number of the device and the eve...

Page 102: ...Adapt the network settings if required If the problem persists contact the network administrator Problem Cause and corrective measure Communication with all devices is dis turbed There is a problem i...

Page 103: ...to USB port 1 Note that the USB data carrier must not be write protected No inverters or not all inverters report back with the version number of the sent update file If you have configured the automa...

Page 104: ...ay the weather or the condition of the PV modules e g pollution or covered with snow To start the update directly perform a manual update see Section 14 2 2 page 76 Energy Meter Problem Cause and corr...

Page 105: ...ve or damaged network components The connection test to the external FTP server failed The data transmission is incorrectly configured Corrective measures Ensure that you have write authorization on t...

Page 106: ...Check the Modbus configuration using the assignment tables and adjust if required see the Technical Description SMA CLUSTER CONTROLLER Modbus Interface The Cluster Controller does not re spond within...

Page 107: ...affected device Corrective measures Contact the Service see Section 20 page 111 The connection test to Sunny Portal has failed The data transmission is incorrectly configured Corrective measures If th...

Page 108: ...stem has been registered twice in Sunny Portal The new Cluster Controller logs into Sunny Portal with a new system identifier Sunny Portal creates a new system for this system identifier even if you h...

Page 109: ...e Cluster Controller is reset to the default settings Stored system data is deleted 3 To exit the display view press ESC 4 To confirm the settings that are to be reset perform the following steps Pres...

Page 110: ...MA Cluster Controller CLCON PWRSUPPLY USB flash drive 4 GB USB flash drive with storage capacity of 4 GB USB FLASHDRV4GB USB flash drive 8 GB USB flash drive with storage capacity of 8 GB USB FLASHDRV...

Page 111: ...al number and the firmware version of the Cluster Controller in the display view Cluster Controller Danmark Deutschland sterreich Schweiz SMA Solar Technology AG Niestetal SMA Online Service Center ww...

Page 112: ...ailand Co Ltd 66 2 670 6999 SMA Technology Korea Co Ltd 82 2 520 2666 South Africa SMA Solar Technology South Africa Pty Ltd Cape Town 08600SUNNY 78669 International 27 0 21 826 0600 Argentina Brasil...

Page 113: ......

Page 114: ...SMA Solar Technology www SMA Solar com...

Reviews: