• Press the shield clamp onto the cable shield.
The cable shield must be clamped under
the shield clamp as completely as possible.
• Depending on the number of connection cables, split the wire required for shielding into
pieces with a length 40 mm.
• Remove 6 mm of the cable sheath and strip
off the insulation by 6 mm at both ends of
the insulated conductor.
• Insert the insulated conductor at one end of
the wire into the ring terminal lug of the
shield clamp and crimp with a crimping
tool.
3. Trim unneeded insulated conductors flush with the cable sheath.
4. Strip off the conductor insulation by 6 mm.
☑ The connection cable is prepared for connection
to the multipole plug.
6 Connection and Commissioning
SMA Solar Technology AG
Installation Manual
31
ClusterController-IA-en-15