7. Transport the MV Power Station to its final position as close to the ground as possible.
8. If the MV Power Station is to be transported directly to the mounting location and installed on the support surface,
attach the support feet (see Section 4.6, page 43).
9. Set the MV Power Station down. The support surface must be suitable for the weight of the MV Power Station in
accordance with the requirements (see "Information on Transport and Mounting of the MV Power Station").
4.4
Transporting the MV Power Station by Truck, Train and Ship
Requirements:
☐ The means of transport must be equipped with container locks.
☐ The doors of the MV Power Station must be closed.
☐ The factory-fitted transport lock on the devices of the MV Power Station must be in place.
☐ If transported by train, the MV Power Station must be loaded on railroad cars with shock absorbers.
Procedure:
1. Load the MV Power Station onto the means of transport (see Section 4.3, page 41).
2. Use container locks to secure the MV Power Station by at least four upper or lower corner castings.
4.5
Removing the Supplied Mounting Material from the MV Power Station
Upon delivery, the supplied mounting material is located in the compartment of the medium-voltage switchgear.
Procedure:
1. Temporarily store the MV Power Station in a suitable location.
2. Open the medium-voltage switchgear compartment (see Section 12.1, page 159).
3. Set up the medium-voltage switchgear service platform (see Section 12.2, page 162).
4. Remove the required mounting material from the medium-voltage switchgear compartment (see Section 16.1
"Scope of Delivery", page 249).
5. Remove the medium-voltage switchgear service platform.
6. Close the medium-voltage switchgear compartment (see Section 12.1, page 159).
4 Transport and Mounting