Instruction Manual StackGuard
20
10266E/1
3.10
Initial commissioning
For the initial commissioning, proceed according to the following table. If faults
occur, see Section 6.
Action Remarks
1.
Make sure that all the components
are correctly installed and con-
nected.
→
Section 3
2.
Connect the voltage supply to the
control unit.
A reading appears on the control
unit display after a few seconds.
3.
Set the language for your region
(
→
The menu text now appears in the
selected language.
4.
Set the measuring range(s) in ac-
cordance with your measuring con-
ditions (
→
5.
Set the relay functions in accor-
dance with your measuring task
(
→
6.
Protect your settings against
unauthorized access with an access
code (
→
Section 4.6).
If you do not require an access
code, you can skip this step