background image

INSTALLING THE TPS9 TVSS

To install the TVSS to the electrical distribution equipment,
proceed as follows:

1.

2.

3.

4.

5.

The voltage rating of the device and system must always
be verified before energizing the TVSS.  All electrical
connections should be performed by a qualified (licensed)
electrician.  All wiring must comply with the National
Electrical Code (NEC) and applicable local codes.

Maintenance of this Transient Voltage Surge
Suppressor should be performed by qualified
electrical personnel only.

During normal operation, hazardous voltages are
present inside the unit.

When servicing this unit, be sure to follow all
electrical safety precautions.

All power sources to this unit should be locked
off before servicing.  This will prevent the risk of
receiving an electrical shock.

WARNING

VERIFY ALL POWER CIRCUITS

ARE DE-ENERGIZED

BEFORE MAKING CONNECTIONS

!

6.

7.

8.

9.

Page 2

BONDING BETWEEN CONDUIT CONNECTIONS

IS NOT

 AUTOMATIC AND MUST BE PROVIDED

AS PART OF THE INSTALLATION.

CONDUCTING DIELECTRIC AND/OR HIGH

POTENTIAL TESTING WILL CAUSE INTERNAL

DAMAGE TO THE TVSS UNIT.  DO NOT PERFORM

DIELECTRIC OR HIGH POTENTIAL TESTS

WITH THE PHASE OR NEUTRAL TVSS

WIRES CONNECTED.

CAUTION

!

If possible, to provide extra rigidity in the installation,
attach the TVSS to the wall or distribution equipment
using installer supplied hardware.
Trim the leads from the TVSS as short as possible, but still
allowing the following connections to be made (see
Figure 2):

Black wires (one, two, or three in number ) go to the
nearest free 20 Amp circuit breaker. The phase of
each lead is marked with a white band and letter
designator (A, B, or C). Connect the TVSS leads to the
appropriate phases. (On High-Leg Delta TPS9’s, the
High-Leg is Phase B, designated with an orange con-
ductor. The orange conductor must be connected to
the system’s High-Leg.)

Connect the white Neutral wire to the neutral bar
using a set screw (in some applications, this connec-
tion may not be required).

Connect the green Ground wire to the electrical distri-
bution equipment ground. Install the distribution
equipment cover.

Note: Conducting dielectric and/or high potential testing
will cause internal damage to the TVSS unit.  DO NOT per-
form dielectric or high potential tests with the phase or
neutral TVSS wires connected.
Apply power to the distribution equipment. Depending on
the TPS9 model, either 1 (single phase applications), 2 (split
phase applications), or 3 (three phase applications) LEDs
will illuminate on the TVSS. If any connected phase LED on
the TVSS does not illuminate, remove power, check all
connections and test again. If any connected phase LED still
does not illuminate, contact Siemens TPS Technical Support
at: 1.888.333.3545.

Ensure power to the electrical distribution equipment has
been removed. Confirm N-G bonding of system per NEC.
Remove the screws securing the outer distribution equip-
ment cover to the distribution equipment (see Figure 1).
Select the location where the TVSS will be mounted (should
be based on the internal configuration of the distribution
equipment and the physical surroundings outside the
equipment). Note that the TVSS’s lead length must be mini-
mized to achieve maximum performance. Once the loca-
tion has been determined, drill or punch a 7/8” diameter
hole in the top, bottom or side surface of the distribution
equipment. The ideal mounting location will also allow the
TVSS to be secured to the wall or panel in addition to using
the chase nipple.
Screw one of the conduit nuts on to the chase nipple until
it bottoms out. Note: bonding of the conduit connections
to the distribution equipment is not automatic, and must
be provided as part of the installation (remove paint from
the distribution equipment surface prior to installing the
TVSS and  chase nipple).
Push the leads from the TVSS through the 7/8” diameter
hole toward the inside of the distribution equipment. Push
the leading part of the chase nipple through the hole and
secure the TVSS using a second conduit nut (sandwiching
the metal wall of the distribution equipment between the
two conduit nuts).

NOTE: 

See Page 4 to connect optional Dry Contact or

Remote Indicator (if equipped).

Summary of Contents for TPS 9

Page 1: ...s TPS 9 Transient Voltage Surge Suppressor User s Manual ...

Page 2: ... the service entrance equipment is not bonded to ground in accordance with the National Electrical Code NEC TESTING HIGH VOLTAGE TESTING DO NOT HI POT TEST Any factory or on site testing of power distribution equipment that exceeds the normal operating voltage such as high potential insulation testing or any other tests where the suppression components will be subjected to voltages higher than the...

Page 3: ...on that will disconnect affected surge protection com ponents at the end of their useful life but will maintain power to the load now unprotected If this situation is undesirable for the application follow these instructions for servicing or replacing the device During installation into an electrical system the TPS9 must NOT be energized until the electrical system is installed inspected and teste...

Page 4: ...round wire to the electrical distri bution equipment ground Install the distribution equipment cover Note Conducting dielectric and or high potential testing will cause internal damage to the TVSS unit DO NOT per form dielectric or high potential tests with the phase or neutral TVSS wires connected Apply power to the distribution equipment Depending on the TPS9 model either 1 single phase applicat...

Page 5: ... High Leg Delta Phase C Black TPS9 TVSS 0 0 0 0 0 0 Distribution Equipment Metal Wall of Distribution Equipment 1234 1234 20 Amp Breaker Figure 2 Typical Parallel Connections Breaker Panel Interconnecting Wiring Minimize Length Avoid Sharp Bends Gently Twist Conductors Together CONDUCTING DIELECTRIC AND OR HI POTENTIAL TESTING WILL CAUSE INTERNAL DAMAGE TO TPS UNIT AND WILL VOID THE UNITS WARRANTY...

Page 6: ...lice latches to the bottom portion of the butt splice The enclosed label should be placed under the LED for reference Plan your installation for adequate label space After installation test the Green LED by energizing then deenergizing the SPD and verifying that the LED turns on and off appropriately An alternate test is to deenergize just one phase CONNECTING TO OPTIONAL DRY CONTACTS IF EQUIPPED ...

Page 7: ... s e h c n i 6 3 e p y T n o i t a l l a t s n I e l p p i N e s a h C s v h t g n e L e r i W d n a e m i T e s n o p s e R e g a t l o V h g u o r h T t e L d n o c e s o n a n 1 e r i w f o m c 7 1 3 t o o f 1 0 2 8 A k 3 V k 6 t o o f r e p s t l o v 5 7 1 e h t o t d e d d a e r a s d n o c e s o r c i m e g a t l o v p m a l c d n a e z i S e r i W e u q r o T n o i t a l l a t s n I s b l n...

Page 8: ...4 4114 ext 1234 seainfo icn siemens com 2006 Siemens Energy Automation Inc All Rights Reserved Siemens is a registered trademark of Siemens AG Product names mentioned may be trademarks or registered trademarks of their respective companies Specifications are subject to change without notice Order PBOM 020205 Rev B 2 5M100DW ...

Reviews: