Procedure
1. The five safety rules (Page 13) must be observed.
2. Install the copper lug supplied for the defective phase.
Figure 9-13
Installing the copper lug for a V circuit
3. To do this, remove the screws from the upper connection of the heat sink module to the
busbar at both sides.
4. Insert the supplied copper lug
①
using the longer eight screws also supplied. The tightening
torque for the screws is 50 Nm.
5. Ensure that the "Emergency operation V circuit" operating mode is activated using
parameter p7006 and is displayed at r7005.
Note
It is not possible to work on the defective module during emergency operation.
Maintenance
9.7 Repairs
SINAMICS SL150 6SL38600UL432AA0Z
102
Operating Instructions Rev.201910281433 EXAMPLE