SINAMICS IOP, Getting Started Guide 01/09 - A5E02449215B2
1
Getting Started Guide
Intelligent Operator Panel (IOP)
Edition: January 2009
Warnings
During commissioning of the Inverter it is essential to ensure that the system is in a safe and
stable state, as some commissioning processes have the potential to start the motor. Therefore
it is important to secure any loads and ensure that should the motor start, no potentially
dangerous conditions exist.
The IOP can be fitted to and removed from the inverter while power is applied.
The IOP will set the USS PZD (P2012) length to 4 when connected to the inverter.