Naturally cooled 1FW6 built-in torque motors
Operating Instructions, 07/2017, 6SN1197-0AF02-0BP2
77
Commissioning
6
The motor can only be commissioned when it has been installed in a machine and integrated
in a functioning system. The commissioning documentation of all the system components,
e.g. the documentation of the drive and encoder system, must be taken into account for the
commissioning. The SINAMICS S120 commissioning manual and these operating
instructions contain important information for commissioning the motor.
6.1
Safety guidelines for commissioning
WARNING
Risk of death and crushing as a result of permanent magnet fields
Severe injury and material damage can result if you do not take into consideration the
safety instructions relating to permanent magnet fields.
•
Refer to Chapter "Danger from strong magnetic fields (Page 24)".
WARNING
injury and material damage if EMC safety requirements are not observed
Risk of death, serious personal injury, and/or material damage can occur if a machine that
does not fulfill the recognized EMC safety requirements is commissioned.
•
Plants and machines with converter-fed low-voltage three-phase motors must fulfill the
protection requirements of EMC Guideline 2014/30/EU.
•
The plant engineer is responsible for ensuring that installation is carried out in an EMC-
compliant manner. Use shielded signal and power cables. Apply the EMC installation
guideline of the converter manufacturer. For Siemens converters, this is available under
document order No. 6FC5297-
□
AD30-0
□
P
□
.