Trimming the Inlet Sampling Tube (See Figure 4)

a. Measure the outside width of the duct.

b. Add 2.25 inches to obtain proper length of tube.

 

Example:

Outside width of duct

2 ft 6in

Add 2.25 inches               +       2.25 in

Length of sampling tube

2 ft 8.25 in

The length (2 ft  8.25 in) determines (Table 1 above) the model

number of the appropriate sampling tube (STA-3).

c. Measure the sampling tube, starting from the end with the four mounting holes.
d. Trim tube to the correct length, remove all burrs, and insert a rubber stopper (Figure 3,

Item 9) in the tube.

b.  

Affix the adhesive backed template (5) to the side of the ductwork.

c.

Drill the four 0.110 diameter holes with a No. 35 drill bit and cut or punch out two 7/8-inch

diameter holes as indicated on the template.

d.

Attach the appropriate model housing to the air duct using two No. 10 1½

 

inch screws (6) and

also using two No. 10 1-inch screws (7) with lockwashers (8).

e.

Cut  a 12 inch by 12 inch access hole in the duct adjacent to the housing to permit checking

and cleaning of the sampling tubes.  The access hole must be covered and sealed when not

in use.

Sampling Tube Selection

To insure accurate air sampling, inlet sampling tubes are available in four lengths. To select the

appropriate length, determine the outside width of the duct.  Select the sampling tube nearest

to, but greater than, the duct width (Table 1).  The outlet sampling tube for all ducts is a fixed

length of 4

 

inches (10.1 cm).  Trim the inlet sampling tube at the job site as described below.

TABLE 1 - Sampling Tube Selection Chart

Outside Duct Width

 

Sampling Tube Model No.    Standard Tube Length

1 ft 9 ¾ in or less

STA-2

  2 ft

1 ft 9 ¾ in - 3 ft 3 ¾ in

STA-3

  3 ft 6 in

3 ft 3 ¾ in - 6 ft 3 ¾ in or less

STA-6

  6 ft 6 in

6 ft 3 ¾ in - 9 ft 9 ¾ in or less

STA-10

10 ft

Greater than 9 ft  9 ¾ in

Consult factory

Note:

Each model is manufactured with a different number and size of hole. Therefore, only

the specific tube must be used for the specified duct width.

Figure 4

Sampling Tube Orientation

Summary of Contents for Cerebrus Pyrotronics SA-11P

Page 1: ...tellite Use Model PE 11 Operation Voltage and Current 120 VAC 50 60 Hz 32A max Alarm Relay DPDT contacts rated at 125 VAC 24 VDC 3A Resistive Trouble Relay SPDT contacts rated at 125 VAC 24 VDC 2A Resistive Smoke Detector Sensitivity Factory set for air duct application See detector nameplate label Alarm Indicator LED on smoke detector displays steady or flashing red light through air duct cover T...

Page 2: ...rs and positioned so as to operate reliably in case of smoke in any part of the air stream In instances where the filters are capable of removing smoke a detector should be installed both upstream and downstream from the filters The air duct detectors because they use sampling tubes which monitor the full width of an air duct overcome the limitations of spot type smoke and heat detectors in the du...

Page 3: ...3 Figure 2 Recommended Locations in Duct Systems Figure 3 Exploded View ...

Page 4: ...ockwashers 8 e Cut a 12 inch by 12 inch access hole in the duct adjacent to the housing to permit checking and cleaning of the sampling tubes The access hole must be covered and sealed when not in use Sampling Tube Selection To insure accurate air sampling inlet sampling tubes are available in four lengths To select the appropriate length determine the outside width of the duct Select the sampling...

Page 5: ...ements should be taken by qualified personnel in accordance with the PDM 3 Instructions P N 315 085535 ELECTRICAL WIRING TheAir Duct Detector Model SA 3I 11P is interconnected and wired following the wiring diagram in Figure 6 Each model requires a two wire circuit of 18 AWG min thermoplastic fixture wire enclosed in conduit or of 18AWG min limited energy shielded cable without conduit if permitte...

Page 6: ... for Models SA 3I and SA 11P CAUTION Do not use looped wire under terminal 5 of the DB 3S or DB 11 base Break wire run to provide supervision of both connections conduit ensure that it is properly connected to the internal metal ground strap using the proper conduit locking nuts Failure to provide proper grounding may result in fatal electrical shock 7 Connect EOL device 1 3K 1 2W resistor to term...

Page 7: ...to place Installation Removal of PE 11 Detector in Base Adapter To Install Align detector with base and insert detector Rotate detector counterclockwise while gently pressing on it until the detector drops fully into base Then rotate the detector clockwise until it stops and locks in place Insert optional locking screw Order Model LK 11 To Remove Rotate the detector counterclockwise until stop is ...

Page 8: ... limits MAINTENANCE The performance of the air duct detector unit may be adversely affected by dirt or foreign matter on the sampling tubes or detector If the air holes in the inlet sampling tube become restricted the unit cannot receive a proper air sample and performance is impaired It is recommended that the sampling tubes be checked and cleaned periodically The detector maintenance program sho...