Infrastructure and Mobility, Traffic Solutions
Sopers Lane, Poole, Dorset
BH17 7ER
Version
7
Page 36 of 76
Status
ISSUED
Last Editor
Ore Oluwatudimu
TS008468
Date
31/01/2017
Document
Name
UPS Solution General Handbook
Doc. No.
667/HB/47750/000
Copyright
Siemens plc 2017 All Rights Reserved
4.
Connect the loose battery connection cable looms to the red connector sockets
on the right side of each Battery Housing module, using the right hand opening in
the base of the Battery Housing module to reach the connector of the housing
below.
NOTE:
in cases where less than three battery housing modules are installed
within the Battery Expansion Cabinet, unused battery cable looms can be
removed and retained as maintenance spares.
9.8 Terminating External Cables into the UPS Connection Panel
Step No.
UPS Cabinet
Battery Expansion Cabinet
Refer to
7
Terminate External cables into
the UPS Connection panel
N/A
Section 9.8
WARNING:
Ensure all power sources are switched off and safely isolated
before installation commences. All switches and MCBs should be in the OFF or
BYPASS position.
1.
Remove the blanking plate from the top of the UPS housing revealing the UPS
Connection Panel.
2.
The DIN rail mounted terminal blocks on the panel are clearly labelled. Cables
are to be terminated according to the following:
o
‘MAINS INPUT’ – Termination for a 3-core cable from the feeder pillar
supply.
o
‘OUTPUT’ – Termination for a 3-core cable to the traffic controller.
o
‘54VDC BUS’ – Termination for internal and Battery Expansion cabinet
battery cables. Clearly labelled ‘+’ and ‘-’.
o
‘C1’ to ‘C6’ – Termination for the UPS solution fault output contacts.
Clearly labelled ‘NO’, ‘C’ and ‘NC’ for Normally Open, Common and
Normally Closed respectively.
Figure 9-9: UPS Connection Panel
3.
Replace the blanking plate.
See section 7 for further details on external cable specification details.