8
Use the open spanner SJGJ-17-19 to disassemble and assemble the bolts and washers in
the blue frame line as shown in the figure, each with 40 pcs.
Save the bolt, washer, and the honeycomb inner corner removed, according to the
position of the mounting place when unpacking the package again.
2.6 Position
In order to ensure smooth and reliable charger, the charger must be vertical basic construction
charger mounted on cement concrete cement based on custom and mounted above the base
level of the ground is not less than 220mm,.
Drilling template according to claim 6 Drill hole depth of 12mm in diameter 100mm in a cement
base, and then through the wall portion of the expansion bolt is inserted in a hole drilled;
Charging the cement foundation piles and reliable ground connection, the ground resistance
must ≤4Ω.
Before installing the charger, it should be checked as follows: the
device is damaged, if damaged, the shipper immediately; product
label check, confirm the correctness of the device. The equipment
label is affixed to the equipment, and the model, capacity and main
parameters are indicated on the label.