background image

INSTALLATIEHANDLEIDING – P24 

VERSION 0129NM02INT01 

INSTALLATION MANUAL – P24  | 

P24

EN

FR

07ANM20INT0

1

Thank you for installing this charge point. Make sure 
there is enough space to properly do the work. 
Ensure to work safely and take the safety of others into 
consideration as well, always work according to local 
safety regulations. Ask the owner if there is anything 
of significant importance that requires electricity in the 
house, before you turn off the electricity.
When selecting the mounting location of the charge point, 
ensure that future maintenance work can be carried out 
safely without obstruction.

4.1 PREPARATION

Step 1: Prepare the cabling & RCD and MCB (conform to 
local rules & regulations);
Step 2: Indicate which circuit in the distribution board is 
connected to the charge point;
Step 3: Turn the socket lid anti-clockwise and out of the 
cover of the charge point;
Step 4: Then pull the cover from the rear edge to open 
the charge point. Do not use any objects or tools to do 
this

4.2 MECHANICAL MOUNT 

Step 1: Put the charge point back plate on the wall to 
check its positioning (connector at +/- 1 m height). On 
the wall, mark the positioning of the top two and bottom 
two attachment points of the charge point and select the 
appropriate fixtures (plugs, screws and washers);
Step 2: Drill all four holes and put the plugs in place; 
Step 3: Secure the charge point to the wall using the top 
two and bottom two attachment points. Ensure that the 
rubber and stainless steel washers are used and placed 
on the back of the charge point at the bottom two 
attachment points

4.3 POWER CONNECTION 

Step 1: Select the appropriate grommet(s) that suits
the cable(s) thickness and place it in the opening of 
the power cable inlet. Lubricate if necessary to make it 
easier to feed the power cable through;
Step 2: Secure the power cable(s) using the cable 
clamp(s);
Step 3: Connect the power to the terminal blocks, as 
indicated in section ‘2.4.1 Overview of Connections’.

Warning

: Keep charge point switched off during 

installation!

4.4 DYNAMIC POWER MANAGEMENT 

MODULE

The Dynamic Power Management Module package 
contains one Dynamic Power Management module, one 
power adapter and one current transformer (CT). The CT 
must be connected at the most upstream point of the 
house grid, closest to the grid connection. Arrows are 
shown on the CT, but direction is not important.
The connection for the CT is located at the bottom of the 
Dynamic Power Management module, and is labelled 
with L1 on the front label. For a 1 phase installed charge 
point the L1 measurement head should match the 
conduction which is connected to the L1 of the terminal 
block.

Although each measuring head is provided with two 
different coloured threads, the polarity of connection is 
not important.

Installation procedure

Step 1: Install the Dynamic Power Management module 
on the DIN Rail in the fuse box;
Step 2: Connect the CT to the Dynamic Power 
Management module, as described in the beginning of 
this paragraph;
Step 3: Apply the CT to the grid connection. Make sure 
to apply the CT so that the total power usage of the 
household is measured on each phase;
Step 4: Connect the power adapter to the Dynamic 
Power Management module. One of the two power 
adapter wires has a broken white stripe. This wire is the 
power adapter GND and should therefore be connected 
to the GND pin (right) on the module. The other wire is 
the +5 Volts and should be connected to the +5V pin 
(left) on the module. The middle pin is not used;
Step 5: Plug the power adapter of the Dynamic Power 
Management Module into a power outlet. The PWR LED 
must light up;
Step 6: The CS LED will (after a few seconds) indicate a 
measured current after the power is on;
Step 7: Clamp a RJ12 connector straight to the UTP 
cable for Dynamic Power Management;
Step 8: Feed the UTP cable(s) through the rubber stop(s) 
on the data cable inlet of the charge point, as indicated 
in section ‘2.4.1 Overview of Connections’;
Step 9: Clamp a RJ12 connector straight to the UTP 
cable for Dynamic Power Management;
Step 10: Check if the RJ12 connectors are OKAY with a 
network cable tester;

4. INSTALLATION PROCEDURE

Summary of Contents for newmotion Home Advanced Edition 7

Page 1: ...100 cm Home Advanced Edition 7 VERSION 07ANM20INT01 2020 MANUEL D INSTALLATION FR INSTRUCTION MANUAL EN...

Page 2: ......

Page 3: ...Table des mati res Table of contents Manuel d installation FR Pages 4 15 Instruction manual EN Pages 16 27 NewMotion Home Advanced Edition 7...

Page 4: ...s pinces d entr e CA doivent tre quip es d une terre ininterrompue des fins de protection Assurez vous que les c bles de connexion sont quip s de fusibles et de disjoncteurs Ne remplacez jamais un l m...

Page 5: ...nale DIN 912 taille 6 Pelle C ble d alimentation Clips de montage pour c ble DDR MCB Pour la configuration locale smartphone avec application d installation C ble UTP CAT5 ou CAT6 Outil de sertissage...

Page 6: ...Interface utilisateur Identification Backoffice de communication Module de gestion dynamique de la puissance de communication 07A _ _ _ _ _ Home Advanced 7 phase unique 32A Home Advanced 7 3 7 kW mono...

Page 7: ...Dimensions Poids Entr e requise Plage d humidit de fonctionnement Plage de temp rature de fonctionnement Certificats Cl ture des exigences de l armoire lectrique 55x25x30 mm 27 gr 5V DC 100mA 5 95 5...

Page 8: ...ION 0129NM02INT01 MANUEL D INSTALLATION P8 P8 EN FR 07ANM20INT01 2 3 APER U DU PRODUIT 2 APER U DES PRODUITS Type 2S EV Prise de courant et couvercle Lecteur RFID tiquette d identification avec num ro...

Page 9: ...ON P9 P9 EN FR 07ANM20INT01 2 APER U DES PRODUITS 2 4 1 APER U DES CONNEXIONS Port Ethernet Poteau de mise la terre Entr e de c ble de donn es UTP avec joint en caoutchouc Entr es pour les c bles lect...

Page 10: ...01 MANUEL D INSTALLATION P10 P10 EN FR 07ANM20INT01 2 APER U DES PRODUITS 2 4 2 APER U DE L INSTALLATION DES ACCESSOIRES P1 Port pour la gestion dynamique de l nergie Entr e de c ble de donn es UTP av...

Page 11: ...5mm Fil solide de 10 mm2 Fil de fer toronn de 6 mm2 avec embouts C ble PE le conducteur PEN n est pas autoris Electrode de mise la terre install e s par ment 100 ohms de r sistance la propagation 230...

Page 12: ...s appropri s l paisseur du des c ble s et placez le s dans l ouverture de l entr e du c ble d alimentation Lubrifiez si n cessaire pour faciliter le passage du c ble d alimentation tape 2 Fixez le s...

Page 13: ...rectement connect s l aide d un testeur de c ble r seau Si la LED du port P1 de la borne de recharge est bleue le module de gestion dynamique de l nergie fonctionne Si elle est rouge la cl de s curit...

Page 14: ...rging by NewMotion demande de scanner un code QR 5 1 VERROUILLAGE DE C BLE Activez la fonction de verrouillage du c ble pour verrouiller en permanence le c ble de charge 5 2 R GLAGE DE LA PUISSANCE S...

Page 15: ...disjoncteur m canique dans votre coffret lectrique attendez 15 secondes et rallumez le VOTRE BORNE DE RECHARGE EST IL MUNIE D UN VOYANT ROUGE CLIGNOTANT Si c est le cas cela signifie que vous utilise...

Page 16: ...he AC input clamps must be fitted with an uninterruptible earth for protection purposes Ensure that the connection cables are fitted with fuses and circuit breakers Never replace a protection componen...

Page 17: ...old separately DIN 912 HEX allen key Size 6 Shovel Power cable Cable mount clips RCD MCB For local configuration smartphone with Installer app UTP cable CAT5 or CAT6 RJ45 UTP cable crimp tool RJ45 con...

Page 18: ...r interface Identification Communication backoffice Communication Dynamic Power Management module 07A _ _ _ _ _ Home Advanced 7 single phase 32A Home Advanced 7 3 7 kW single phase 16A Class I Type 2S...

Page 19: ...IONS CONTINUED 2 PRODUCT OVERVIEW P1 DONGLE SPECIFICATIONS Stand by consumption Operating temperature range Operating humidity range Operating air pressure range Maximum mounting height socket Advised...

Page 20: ...P20 VERSION 0129NM02INT01 INSTALLATION MANUAL P20 P20 EN FR 07ANM20INT01 2 3 OVERVIEW OF PRODUCT 2 PRODUCT OVERVIEW Type 2S EV Plug socket cover lid RFID Reader Identification label with serial numbe...

Page 21: ...EHANDLEIDING P21 VERSION 0129NM02INT01 INSTALLATION MANUAL P21 P21 EN FR 07ANM20INT01 2 PRODUCT OVERVIEW 2 4 1 OVERVIEW OF CONNECTIONS Earthing pole Inlets for power cables Power cables clamps Phase 1...

Page 22: ...2 VERSION 0129NM02INT01 INSTALLATION MANUAL P22 P22 EN FR 07ANM20INT01 2 PRODUCT OVERVIEW 2 4 2 OVERVIEW INSTALLING ACCESSORIES P1 Port for Dynamic Power Management UTP data cable inlet with rubber se...

Page 23: ...nded wire with ferrules PE cable PEN conductor is not allowed Separately installed grounding electrode 100 Ohm spreading resistance 230V N 10 50Hz Cable grommets sizes Maximum cable terminal block TN...

Page 24: ...Warning Keep charge point switched off during installation 4 4 DYNAMIC POWER MANAGEMENT MODULE The Dynamic Power Management Module package contains one Dynamic Power Management module one power adapt...

Page 25: ...e P1 port the cable is not correctly connected 4 5 FINISHING UP Step 1 Check and make sure that the rubber seal of the casing is properly in place on the edge Step 2 Place the cover on the charge poin...

Page 26: ...n which is included in the charge point package when the Installer App requests to scan a QR Code 5 1 CABLE LOCK Enable the cable lock feature to permanently lock the charge cable 5 2 POWER SETTING Se...

Page 27: ...n your fuse box wait 15 seconds and turn it back on IS THERE A BLINKING RED LED LIGHT ON YOUR CHARGE POINT If so it means you are using a card which is not linked to the charge point by your installer...

Page 28: ......

Reviews: