05. Installation
-How to use assemble pipe lines
1) Please check if all parts are in the package;
-1 panel of 1 Flow meter and valve,
-3 pipe lines with nuts,
-1 Gas gauge with valve
Fig-3) In case of Pipe parts for 2 gas channels; 1 panel of 2 Flow-meters and valves, 4 pipe
lines with nuts, 1 Gas gauge with valve.
Fig-3)
Fig-2)