Installation
13
Doc 01-G0665
Rev A
Pad Mount Installation
1
Lay out the concrete pad as detailed. Concrete depth should be below frost
line or as required by local codes. Operator cabinets may be installed either
parallel to the fence, the SW470 only perpendicular to the fence.
CAUTION
Be sure that the measurements for the operator mounting are from the
centerline of the fence and centerline of gate hinge.
2
Locate electrical conduit, as required, prior to pouring concrete.
3
Pour concrete, insuring that pad is level and above ground line.
4
Locate (4) ½” X 6” minimum length L-Bolts (not supplied). These should
protrude (1) inch above pad.
5
Allow concrete to set at least two days before installing power unit.
6
After concrete has set, carefully secure operator to concrete pad, in correct
relative secure operator to concrete pad, in correct relative position. The L-
Bolts will protrude through the holes in the mounting flanges and should be
secured with hex nuts and lockwashers (not provided).
It is very important that the operator is level and parallel to the gate.
DIMENSION TABLE
A B C D
SW470
9-3/4” 22-1/2” 24”
8”
SW490
16” 28” 32” 8”
Table 6
01-G0665F2
Figure 6