SEELEY INTERNATIONAL Braemar Ecostar TQ3 Installation Manual Download Page 15

14

SEELEY INTERNATIONAL –

 

INSTALLATION MANUAL

Check high gas

High gas pressure:

 - Natural Gas   Nominal 875 Pa (825 to 925 Pa)

- Propane 

Nominal 2250 Pa (2050 to 2450 Pa)

Adjust only if outside this range

USE LARGE HIGH GAS ADJUSTMENT SCREW - hold small

adjustment screw still

Check low gas

Remove one lead from modulating coil (LOW VOLTAGE, 0-17 Vdc)

Low gas pressure:

 - Natural Gas   Nominal 100 Pa (90 to 110 Pa)

- Propane

Nominal 180 Pa (170 to 190 Pa)

Adjust only if outside this range

USE SMALL LOW GAS ADJUSTMENT SCREW - hold large

adjustment screw still

Re-check high gas

Re-connect lead to modulating coil

High gas pressure:

 - Natural Gas   Nominal 875 Pa (825 to 925 Pa)

- Propane

Nominal 2250 Pa (2050 to 2450 Pa)

Adjust only if outside this range

USE LARGE HIGH GAS ADJUSTMENT SCREW - hold small

adjustment screw still

High gas 

adjustment

screw

Low gas 

adjustment

screw

Modulating 

coil leads

Outlet pressure 

test point

ENSURE BOTH 

LEADS ARE 

CONNECTED TO 

MODULATING COIL 

WHEN FINISHED

Run heater and check pressure at outlet test point, adjust if 

necessary:

- All natural gas models:  875 +/- 50 Pa

Run heater on HIGH and check pressure at outlet test point, 

adjust if necessary:

- All natural gas models:   

875 +/- 50 Pa (980 +/- 50 Pa for TQ435) 

- Propane models:

- TQ4/15/20/25 

2500 +/- 200Pa

- TQ430   

1900 +/- 200Pa

- TQ516   

2500 +/- 200Pa

- TQ23/32 

1700 +/- 200Pa

Reduce fan speed and allow heater to switch to LOW and 

check pressure at outlet test point:

- All natural gas models:  

400 +/- 20 Pa (450 +/- 20 Pa for TQ435)

- Propane models:

- TQ4/15/20/25 

1100 +/- 100Pa

- TQ430   

1000 +/- 100Pa

- TQ516   

1100 +/- 100Pa

- TQ23/32 

800   +/- 100Pa 

OUTLET PRESSURE 

TEST POINT

REGULATOR 

ADJUSTMENT 

COVER

OUTLET PRESSURE 

TEST POINT

LOW PRESSURE 

ADJUSTMENT

HIGH PRESSURE 

ADJUSTMENT

Gas Out

Gas Out

COMMISSIONING - INSTALLER OR COMMISSIONING AGENT

Installation checks

Check for gas leaks - rectify any leaks found.

- Natural Gas 1.13kPa

- Propane 2.75kPa

Check for gas leaks - rectify any leaks found.

Check that the flue system is connected, sealed and installed with appropriate clearances.

Check that Controller is wired correctly and installed in a suitable location.

Check that the heater is level in both directions (critical for TQ5, TQM6, TQS5, TQS6 heaters to allow correct drainage of condensate).

Gas pressure checks

Connect a manometer to the outlet pressure test point on the gas valve.

Start heater as described in Owner’s Manual.

Wait 30 seconds after heater lights to ensure heater has reached high gas rate.

Commissioning continued 

Modulating heaters

Commissioning continued 

Non modulating heaters 

TQM516
TQM520

TQM5X20

TQM530

TQM618

TQM623

TQM6X23

TQM5X30

TQM632

TQM6X32

TQS420

TQS4X20

TQS523

TQS5X23

TQS623

TQS6X23

TQ315
TQ320

TQ3X20

TQ325

TQ3X25

TQ330

TQ3X30

Single stage gas valve

Two stage gas valve

TQ415
TQ420

TQ4X20

TQ425

TQ4X25

TQ430

TQ4X30

TQ435
TQ516

TQ523

TQ5X23

TQ532

TQ5X32
TQS320

TQS3X20

INLET PRESSURE TEST 

POINT

INLET PRESSURE TEST 

POINT

INLET PRESSURE TEST 

POINT

Summary of Contents for Braemar Ecostar TQ3

Page 1: ...Braemar Ecostar TQ3 TQ4 TQ5 TQM5 and TQM6 Gas Ducted Heater Braemar Supernova TQS3 TQS4 TQS5 and TQS6 Gas Ducted Heater INSTALLATION MANUAL ...

Page 2: ...1 TQ3 TQ4 TQ5 TQM5 TQM6 TQS3 TQS4 TQS5 TQS6 ...

Page 3: ...guide to contractors and employees to assist in minimising risk Risk Assessment A risk assessment of all hazardous tasks is required under legislation A risk assessment is an essential element that should be conducted before the commencement of work to identify and eliminate the risk of falls and other risks or to minimise these risks by implementing control measures This does not need to be a com...

Page 4: ...ng loom at the plug near the top of the centre panels Disconnect the combustion fan suction hose connected to pressure switches or hose connector depending on heater model Disconnect the ignition lead flame sense lead and flame rollout lead from the ICS PCB and feed through the grommet in the centre panel This is easiest to do with the grommet removed from the panel Remove the two retaining screws...

Page 5: ...s via a 24Vac relay to switch the cooling system on and off A MagIQ link module is required to connect the Braemar Invertair inverter add on cooling system to the heater Ensure ADD ON COOLER and GAS DUCTED HEATER is selected at the Appliance types screen during system setup on the MagIQtouch Controller to enable the system to operate the Braemar add on cooling system 4 Fit side panels back to heat...

Page 6: ...nstalled in the floor should discharge sideways Registers installed in the ceiling should discharge predominantly vertically 1 Based on standard 100 x 300mm floor outlets and 150mm round ceiling outlets 2 Minimum outlets open to achieve optimum turndown performance 3 X in model refers to extra air models maximum outlets will be reduced when a add on cooling coil is installed Additional notes For h...

Page 7: ...uch Controller Master MagIQtouch Air Sensor systems ensure that the COMMON zone is always heated even if it is only a small air flow The common zone must include a return air grille Explain to the customer the function of the return air duct and the need for a clear air path to the return air grille air cannot travel through closed doors DO NOT in any way obstruct the flow of return air For Single...

Page 8: ...h a separate circuit breaker Wiring must be installed in accordance with the relevant electrical standards regulations The electrical supply must be 240V 50Hz A conventional 10A 3 pin 240V GPO must be fitted adjacent to the heater Ensure that the polarity of the power supply is correct If the supply cord is damaged it must be replaced by the manufacturer its service agent or similarly qualified pe...

Page 9: ...079073 077420 TQM5X30 NA NA NA 075006 075556 075556 094939 094922 075587 094328 076898 076362 076386 079073 077420 TQ516 NA NA NA 075525 075532 075525 094939 094922 075587 094328 076898 075990 076034 NA NA TQ523 NA NA NA 075525 075532 075525 094939 094922 075587 094328 076898 075990 076034 NA NA TQ5X23 NA NA NA 075525 075532 075525 094939 094922 075587 094328 076898 075990 076034 NA NA TQ532 NA NA...

Page 10: ... 400 555 330 687 609 83 TQ3X20 TQ4X20 385 660 574 25 770 202 383 735 415 244 350 555 332 695 625 55 TQ3X25 TQ4X25 385 660 574 25 770 202 383 735 415 244 350 555 332 695 625 55 TQ3X30 TQ4X30 510 660 557 25 880 200 415 767 415 240 400 555 330 687 609 83 TQ516 385 660 574 25 1150 535 765 1067 395 244 300 578 670 1003 625 55 TQ523 385 660 574 25 1150 535 765 1067 395 244 300 578 670 1003 625 55 TQ532 ...

Page 11: ...le location Fix flue in place with screw Remove discard lower transit plug Check that upper transit plug is secure External flue terminal External flue terminal stainless steel Fix in place with screw Heater flue outlet spigot A flue terminal and condensate drain elbow are supplied in TQM TQS6 external installation accessories kit P No 075570 Heaters Heaters Heaters Heaters TQ516 TQ523 TQ5X23 TQ53...

Page 12: ...OOM FAN END OF HEATER Ensure 200mm minimum clearance above heater Service maintenance platform 19mm particle board or equivalent HEATER LOCATION AVOID QUIET AREAS Above bedrooms living room lounge room dining room etc PREFERRED LOCATIONS Above laundry bathroom kitchen garage etc Flue E A A 385 or 510 Depends on model See page 9 E 770 880 1160 Depends on model see Heater Dimensions page 750 Min Gas...

Page 13: ...embly Flue drain elbow Vent cowl Flue drain hose SEAL CONNECTIONS Seal flue and condensate drain connections using silicone sealant or PVC primer and solvent cement INSULATE DRAIN LINE Fit insulation eg Armaflex over full length of condensate drain line in sub zero climates FLOOR concrete base DUCT HEATER FLUE External Wall 200mm minimum for servicing Flue to terminate outside building Light switc...

Page 14: ...f a downpipe via a tundish Condensate drain must run down hill from connection point on heater to point of discharge do not allow any part to run up hill Condensate drain must be well supported Do not allow condensate to be discharged into any potable water system or potable water system collection point Fit insulation eg Armaflex over full length of condensate drain line in sub zero climates INST...

Page 15: ...switch to LOW and check pressure at outlet test point All natural gas models 400 20 Pa 450 20 Pa for TQ435 Propane models TQ4 15 20 25 1100 100Pa TQ430 1000 100Pa TQ516 1100 100Pa TQ23 32 800 100Pa OUTLET PRESSURE TEST POINT REGULATOR ADJUSTMENT COVER OUTLET PRESSURE TEST POINT LOW PRESSURE ADJUSTMENT HIGH PRESSURE ADJUSTMENT Gas Out Gas Out COMMISSIONING INSTALLER OR COMMISSIONING AGENT Installat...

Page 16: ...S6 Heaters Before turning the MagIQtouch Controller on ensure all components have been connected to the system It is very important when stepping through the Wall Control system installation wizard that you follow each prompt carefully to ensure that the system is configured correctly NOTE if you have multiple evaporative coolers refer cooler installation manual ADJUSTING MAXIMUM FAN SPEEDS AFTER ...

Page 17: ...as supply Min supply pressure 1 13 kPa NG Has gas meter been installed Turn gas on at gas meter Controller not connected Connect manual 2 wire thermostat to MANUAL T STAT terminals on ICS Connect MagIQtouch Controller to WALL CONTROL terminals on ICS No Controller communication Refer to System Setup section of this manual MagIQtouch Controller not calling for heat Adjust set point above current ro...

Page 18: ...ly voltage out of range L2 23 Room fan not running L2 24 Room fan running backwards L1 25 Condensate wiring FLAG incorrect L1 26 Gas rates wiring FLAG incorrect L1 27 Thermistor wiring FLAG incorrect L1 28 Modulating wiring FLAG incorrect L1 30 Loom ID incorrect L1 31 Combustion air pressure prior to start L1 32 Combustion air pressure too low at start L2 33 Gas relay High error L2 34 Gas relay Lo...

Page 19: ......

Page 20: ...ational com It is the policy of Seeley International to introduce continual product improvement Accordingly specifications are subject to change without notice Please consult with your dealer to confirm the specifications of the model selected www braemar com au ...