7. HEATER ASSEMBLY
Tools Needed: (not supplied)
Adjustable Wrench, Slip Joint Pliers, Phillips Screwdriver-Medium Blade (#2 or #3 blade), Ham-
mer, 3/8” Masonry Drill Bit (if mounting on concrete patio), Plumbing Seal/Tape for Joints, Spray
Bottle of Soapy Water or Paint Brush and soapy water (leak testing)
1. Using nuts and bolts
supplied, fasten the post
stub plate to the base
cover.
2. Align access port in post to
slot in post stub.
Secure the post to the stub
using screws supplied.
5. Tip post/base assembly on its side.
The gas hose can be connected to the gas supply either:
With hose extended under the heater base (typical)
Gas connection is concealed and protected under
heater base
With hose out through the access port in the post
Gas connection is exposed - sidewall/above deck con-
nection
Ensure exposed gas hose is protected from physical
damage
6. Make connection from gas supply to gas hose
Note: Concealed gas connection under heater: Once
heater is fully installed, temporary access to concealed
connections in the gas supply will be required for leak
testing
OR
3. Connect gas hose to burner and secure connection with a
wrench.
4. Feed gas hose and 24V wire down the post and temporarily
secure the burner assembly to post with screws supplied.
HAND TIGHTEN the fastening screws at this time. When the
heater is connected to the gas supply, the burner head will
need to be lifted to leak test the hose connection to the
burner valve.