2.4. Joining channels 

Channels can be extended with joiners: 

 

 

 

 

 

 

 

 

2.5. Earthing 

Every solar PV installation needs to comply with applicable codes and standards, including for 

earthing the PV module frame and array frame. On each SECT, the module frames are 

electrically earthed to the array frames via the stainless-steel module clamp plates. Each 

module is held using two clamps plates. Each clamp plate has two sharp edges that penetrate 

the aluminium oxide layer on the frame of the solar module. Thus, if the array frame is earthed 

(using the SPEL earth lug) then the module frame will also be earthed, and vice versa. Note 

that the array frame components are mill finish (non-anodized) aluminium, so do not have an 

anodized layer that needs to be pierced.  

 

 

 

 

 

 

 

 

 

 

SPCJ02 (bottom 

 

SECT module clamp plate (highlighted in green) on edge bracket,  

SECT earth lug SPEL 

and on flush bracket. 

on centre bracket,  

Summary of Contents for SECT

Page 1: ...SECT INSTALLATION MANUAL SECT patent pending in flush north or east west variants...

Page 2: ...ptions 4 1 4 No reach installation 5 1 5 Types of roof fixings 5 2 LAYOUT AND ASSEMBLY 6 2 1 Fixing spacing 6 2 2 Length of column or row 6 2 3 Assembly 7 2 4 Joining channels 9 2 5 Earthing 9 3 INSTA...

Page 3: ...anning installation and commissioning of the solar power system must only be performed by qualified technical personnel Improper execution can result in damage to the system and premises and endanger...

Page 4: ...the same orientation also called north 0 tilt also called flush 1 2 Compliance and certification SECT is supplied with a generic certification that suits most buildings covering wind regions A B C ter...

Page 5: ...e Assembly occurs by sliding the far edge of the module into the C shaped profile then clamping at the near edge This way installers don t have to reach a meter over the module to tighten a fastener 1...

Page 6: ...to the roof sheet rib spacing However the purlin spacing needs to match the approved clamping zones defined by the module installation manual e g from 1000 to 1600 mm to fit the typical 10 25 clamping...

Page 7: ...cers 3 Position the first module then fix the module to the channel using two edge brackets 4 Slide the far edge of the first module into the C sections offered by the edge brackets then position two...

Page 8: ...ar using the same brackets Note that the edge brackets are always oriented so that the stainless steel clamp plate faces the module Assembly of SECT flush is even simpler using the SPFB 40 flush brack...

Page 9: ...ainless steel module clamp plates Each module is held using two clamps plates Each clamp plate has two sharp edges that penetrate the aluminium oxide layer on the frame of the solar module Thus if the...

Page 10: ...mps should be installed directly on top of the purlin i e on top of the concealed clip which holds the roof sheet to the purlin Channel should be extended past the last module frame to overlap the nex...

Page 11: ...e with all common roofing materials including galvanized iron Zincalume and Colorbond Therefore the aluminium channel foot is permitted to directly contact the roof sheet However SECT recommends the u...

Page 12: ...hole in the base to suit a M8 anchor 6 CABLE TRAYS 6 1 Cable trays on a sheet metal roof SECT channel and channel lid and channel feet can be used as an alternative to galvanized steel cable tray Chan...

Page 13: ...tray Fasteners are Masonry Torx Screw 7 5 mm diameter x 40 mm length part 1CCT1C407 5040 into a pre drilled 6 mm diameter hole 6 3 Cable trays on another channel Channel as cable tray can be fixed on...

Page 14: ...lectrical installation including DC cabling DC isolators inverter and AC cabling is conducted using standard solar PV installation methods and procedures The SECT frame is fabricated from mill finish...

Page 15: ...0 0 SCHLETTER SOLAR GMBH Alustrasse 1 83527 Kirchdorf GERMANY www schletter group com We reserve the right to changes including technical modification...

Reviews: