Schebler eVent Installation Instructions, Operation And Maintenance Manual Download Page 10

10 

 

Proper performance and long service life of the Model eVent 
Series Venting System requires that the vent be rigidly braced and 
supported.  Every installation offers unique support and bracing 
requirements and the following guidelines will provide minimum 
acceptable sizes for the mechanical hardware supplied by others. 
When the support plate is bolted to framework 3/8” bolts should 
be used in all of the holes on the perimeter of the support plate. 

 

 

 
 
 
 

 

 
 
 

 
 
 

 

Figure 28 – Support Plate Bracing 

INSULATED THIMBLE (IT) 

 

The insulated thimble is used in conjunction with the flashing 
and rain collar when clearances to combustibles cannot be 
maintained at a roof penetration. The Insulated Thimble should 
be dropped through the roof opening. The (4) four tabs will set 
upon the roof deck and nailed or bolted down. The flashing is 
then set over the Insulated Thimble. 
 
 
 
 
 
 

 
 

 

 

Figure 29 – Insulated Thimble 

 

RAIN CAP (CC) 

 

The Rain Cap provides partial protection from rain and debris.  
The Rain Cap is mounted on the end of a standard pipe section 
with the use of an inner band.  A closure ring is provided to 
close off the space between the inner and outer liners.  A 
minimum clearance of 8 feet (2.44 m) is recommended to 
ensure that all exhausted products are dispersed away from 
the building and intakes.  To install the Rain Cap, the following 
procedure should be used: 

1.

 

Install the Rain Cap on the inner flange and attach the 
"V" band using the inner joint instructions. 

2.

 

Install the provided skirt section as shown below. 

3.

 

Apply a silicone sealant to fill all gaps and joints on the 
collar and tighten all bolts. 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

 

 

Figure 30 – Rain Cap Assembly 

 

To clean the flue or replace the Rain Cap, reverse the above 
procedure.  To reinstall, follow the installation procedure.

  

5" -   20"

2 x 2 x 3/16

22" - 36"

3 x 3 x 1/4

6 x 2 x 3/8 or 

equivalent

38" - 48"

4 x 4 x 3/8

eVent Series Size

Framework

Bracing

5 x 2 x 3/16 to 6 x 2 x 

3/16 or equivalent

2 x 1 x 3/16 to 5 x 2 x 

3/16 or equivalent

eVent SERIES SUPPORT LIMITS 

SECTION INSIDE 

DIA. 

SUPPORT PLATE (SP) 

WALL SUPPORT (WS) 

inches mm  feet meters  feet meters 

5-6 127-152 403  122.83  193  58.83 
7-8 178-203 389  118.60  171  52.12 

9-10 228-254  375  114.36 

164  49.99 

11-12 279-305  361  110.12 

153 

46.63 

13-14 330-356  347  105.89 

148 

45.11 

15-16 381-406  334  101.65 

140 

42.67 

17-18 

431-457 

320 97.41  134 40.84 

19-20 

482-508 

306 93.18  129 39.32 

21-22 

533-559 

292 88.94  123 37.49 

23-24 

584-610 

278 84.70  119 36.27 

25-26 

635-660 

264 80.47  113 34.44 

27-28 

686-711 

250 76.23  108 32.92 

29-30 

736-762 

236 71.99  103 31.38 

31-32 

787-813 

222 67.76  120 36.58 

33-34 

838-864 

208 63.52  114 34.75 

35-36 889-914  195 

59.28 

88 

26.82 

37-38 940-965  181 

55.05 

81 

24.69 

39-40 990-1016  167 

50.81 

77 

23.47 

41-42 1041-1067  153 

46.57 

73 

22.25 

43-44 1092-1118  139 

42.34 

68 

20.73 

45-46 1143-1168  125 

38.10 

64 

19.51 

47-48 1194-1219  111 

33.86 

60 

18.29 

 

Summary of Contents for eVent

Page 1: ...sing Boiler Systems A MAJOR CAUSE OF VENT RELATED FIRES IS FAILURE TO MAINTAIN REQUIRED CLEARANCES AIR SPACES TO COMBUSTIBLE MATERIALS IT IS OF UTMOST IMPORTANCE THAT THIS VENT BE INSTALLED ONLY IN AC...

Page 2: ...ion GS 12 Operating Precautions 13 Maintenance 13 GENERAL These instructions cover installation requirements for the Schebler listed single and double wall special stainless steel venting systems eVen...

Page 3: ...pliance It is recommended that venting systems be enclosed below the roof line to limit condensation and protect against mechanical damage Methods of providing additional insulation may be specified I...

Page 4: ...being vented TERMINATION HEIGHT REQUIREMENTS Vents are to terminate a minimum of 3 ft 0 92 m above the highest point of the roof penetration and 2 ft 0 61m minimum above any portion of a building wit...

Page 5: ...ent eVentPLUS and eVentPLUS2 INDIVIDUAL PART INSTALLATION This section identifies Models eVentSW eVent eVentPLUS and eVentPLUS2 by name and part number or part code See the section titled Part Identif...

Page 6: ...allations install the weld seam along the top of the duct See figure 8 below Step 4 Make a single true cut through both gasket layers Remove excess gasket material and position cut ends such that they...

Page 7: ...W eVent eVent Plus2 has a 1 drain pipe that must be connected to a suitable drain The Drain Tee Cap must be connected at all times to a suitable drain Upon entering the vent rain will wash down and re...

Page 8: ...er band end clips allowing the V to be clamped between the split plates and split clamp flanges Installation for the Wall Support is accomplished with the following procedure 1 Connect the joint to be...

Page 9: ...greatest strength for support of the eVent Series Venting System It will provide vertical support and will provide for joint alignment and support for horizontal applications Locate and secure the Sup...

Page 10: ...following procedure should be used 1 Install the Rain Cap on the inner flange and attach the V band using the inner joint instructions 2 Install the provided skirt section as shown below 3 Apply a sil...

Page 11: ...Section While 3 guys are usually sufficient it is recommended that 4 equally spaced wires at an angle of 45 from the vertical be utilized The cables and guys must be slightly loose to allow for the th...

Page 12: ...located at a joint connection The Guy Section is comprised of four 4 half flanges and is bolted together as shown in figure 39 below with the supplied hardware The outer shell is then sealed by using...

Page 13: ...ANCE Venting and Exhaust Systems 1 After the installation of the vent or exhaust system ensure that the required clearances are maintained and that the system continues to be supported properly 2 The...

Page 14: ...14 February 2019 5665 Fenno Rd Bettendorf IA 52722 www Scheblerchimney com Phone 563 359 0110 Fax 563 359 8430...

Reviews: