Assembly and operating instructions Type ALD1B5FS
32 A bidirectional Single Phase active power energy meter with S-Bus interface, Pic. 1
Description
Energy meter with S-Bus interface enables the reading of all
relevant data like meter reading, electricity, voltage, power
(active and reactive) and cos phi.
Indicating elements (Pic. 4)
T (kWh)
■
Indicates the total consumption
T (kWh)
■
Indicates the total feeding back
P (kW)
■
Indicates the instantaneous power
Current = consumption (pos.)
Current = feeding back (neg.)
U (V)
■
Indicates the voltage
I (A)
■
Indicates the current
2000 pulses/kWh
■
Pulsates according to the amount
of used power.
Technical data
Connection
■
Pic. 2
diagram
Dimensions
■
Pic. 3
Accuracy class
■
B according to EN50470-3,
1 according to IEC62053-21
Reference, Maxi-
■
I
ref
= 5 A, Im
ax
= 32 A, Ist
=
20 mA
mum, initial current
operating voltage
■
230 V
AC
, 50 Hz
Tolerance −20%/+15%
Counting range
■
00 000,00…999 999,9 kWh
Connections
■
Conductor cross-section max. 6 mm
2
,
Main circuit
screwdriver pozi no. 1, slot no. 1,
torque 1,2 Nm
Connections
■
Conductor cross-section max. 2,5 mm
2
,
Control circuit
screwdriver pozi no. 0, slot no.1,
torque 0,5 Nm
Operating
■
−25… +55°C (noncondensing
temperature
according standard EN50470)
Environment
■
Mechanical M2
Electromagnetic E2
Notes before connecting
In order to avoid moisture in the meter due to condensate
build-up, acclimatise the meter at room temperature for
about half an hour before connecting.
Attention!
These devices must only be installed by a professional
electrician, otherwise there is the risk of fire or the risk of
an electric shock.
Declaration of Conformity CE
We, Saia-Burgess Controls Ltd., CH 3280 Murten (Switzer-
land), herewith declare, on our own responsibility that
the products:
■
ALD1B5FS00A3A00
which this certificate refer to, are in accordance with the
directive 2004/22/EG (MID) and the following standards:
■
EN50470 parts 1 and 3 (electronic meter), of
October
2006.
ESD on equipment side: 13 kV.
Murten, 30.04.2013
Conformity Assessment Body:
METAS-Cert, Nr. 1259
CH-3003
Bern-Wabern
Signed: Urs Tanner, Site Quality Leader
English
Installation instructions
The energy meter can be attached to a 35 mm rail
(EN60715TH35).
The meter can be used only in installation cabinets.
Operation of the LCD display
See page with LCD menu navigation.
4 319 5139 0E
03.2017
Subject to change without notice
Method of operation
Energy is added as indicated by the arithmetic operator.
Positive output in the meter indicates that energy is being
supplied, while negative output indicates that energy is
being delivered.