8

    S&C Instruction Sheet 1025-511

Installation

Installing the Rack-Mounted GridMaster 

Controller 

Rack-mounted GridMaster controllers can be installed in 
a standard 1U slot in a 19-inch (483-mm) equipment rack. 

To install the GridMaster controller into an equipment 

rack:

STEP  1.  

Use best practices for installing rack equipment 
by installing the heaviest equipment on the 
bottom of the rack. On taller racks, this prevents 
the equipment rack from becoming top heavy. 
The GridMaster controller is lightweight at only 
8 lbs (3.6 kg) and can be installed toward the top 
of the rack. 

STEP  2.  

Slide the microgrid controller into a 1U slot and 
use the appropriately sized mounting screws 
(10-32, 12-24, and M6 screws are most common) 
to install the GridMaster controller to the rack. 
See Figure 2. For installation in a rack without 
threaded holes, cage nuts and screws are 
recommended. Tighten the screws.

Figure 2. Rack dimensions and mounting hole centers.

464 mm

32 mm

44 mm

483 mm

Summary of Contents for IPERC GridMaster

Page 1: ...cation 2 Operating Considerations 2 Special Warranty Provisions 3 Warranty Qualifications 3 Safety Information Understanding Safety Alert Messages 4 Following Safety Instructions 4 Replacement Instruc...

Page 2: ...on sheet is a permanent part of your GridMaster Microgrid Control System Designate a location where you can easily retrieve and refer to this publication Proper Application WARNING A GridMaster contro...

Page 3: ...nty does not apply to any equipment that has been disassembled repaired or altered by anyone other than the seller This limited warranty is granted only to the immediate purchaser or if the equipment...

Page 4: ...ortant procedures or requirements that can result in product or property damage if instructions are not followed Following Safety Instructions If you do not understand any portion of this instruction...

Page 5: ...fied persons See the Qualified Persons section on page 2 2 SAFETY PROCEDURES Always follow safe operating procedures and rules 3 PERSONAL PROTECTIVE EQUIPMENT Always use suitable protective equipment...

Page 6: ...fy the delivering carrier immediately 2 Ask for a carrier inspection 3 Note the condition of shipment on all copies of the delivery receipt 4 File a claim with the carrier If concealed damage is disco...

Page 7: ...ion Before Starting Familiarize yourself with the parts of the GridMaster controller See Figure 1 Figure 1 GridMaster controller rear view On Off Switch Power LED Blank Plate for Options Terminal 1 Te...

Page 8: ...herack Ontallerracks thisprevents the equipment rack from becoming top heavy The GridMaster controller is lightweight at only 8 lbs 3 6 kg and can be installed toward the top of the rack STEP 2 Slide...

Page 9: ...ontroller for at least one hour after control power is lost STEP 5 If the associated IED communicates via Ethernet connectasolid copperEthernetcable to the Ethernet 1 port Connect the other end to the...

Page 10: ...t 1025 530 check the following STEP 1 Make sure the GridMaster controller is securely installed in the rack Check all fasteners for tightness STEP 2 Make sure all cable connections and wiring connecti...

Page 11: ...Operating Temperature 20 C to 50 C 4 F to 122 F Operating Humidity 95 non condensing humidity Altitude 3000 meters 9843 feet Module Pinouts Terminal 1 and Terminal 2 Pin Function 1 Data TX 2 Data TX...