20
EB 8139 EN
Mounting and start-up
5.4 Quick check
Tight shut-off
1. Close the valve.
2. Slowly open the shut-off valve in the
pipeline.
Risk of valve damage due to a sudden
pressure increase and resulting high flow
velocities.
Slowly open the shut-off valve in the pipeline
during start-up.
3. Check the valve for leakage (visual in-
spection).
Fail-safe position
Î
Shut off the signal pressure line.
Î
Check whether the valve moves to the
fail-safe position.
Pressure test
During the pressure test, make sure the fol-
lowing conditions are met:
−
Retract the plug stem to open the valve.
−
Observe the maximum permissible pres-
sure for valve and plant.
The plant operator is responsible for per
-
forming the pressure test. SAMSON's Af
-
ter-sales Service department can support you
to plan and perform a pressure test for your
plant.
NOTICE
!
Note