6-2
EB 8055 EN
Start-up
Before start-up or putting the valve back into
service, make sure the following conditions
are met:
−
The valve is properly installed into the
pipeline (see the 'Installation' section).
−
The leak and function tests have been
completed successfully (see the 'Testing
the installed valve' section).
−
The prevailing conditions in the plant
section concerned meet the valve sizing
requirements (see information under 'In
-
tended use' in the 'Safety instructions
and measures' section).
Start-up/putting the valve back into opera
-
tion
1.
Allow the valve to cool down or warm up
to reach ambient temperature before
start-up when the ambient temperature
and process medium temperature differ
greatly or the medium properties require
such a measure.
2.
Slowly open the shut-off valves in the
pipeline. Slowly opening these valves
prevents a sudden surge in pressure and
high flow velocities which can damage
the valve.
3. Check the valve to ensure it functions
properly.
Summary of Contents for 3253
Page 22: ...3 8 EB 8055 EN...
Page 27: ...EB 8055 EN 4 5 Shipment and on site transport...
Page 28: ...4 6 EB 8055 EN...
Page 74: ...12 2 EB 8055 EN...
Page 76: ...13 2 EB 8055 EN...
Page 79: ...EB 8055 EN 14 3...
Page 80: ...14 4 EB 8055 EN...
Page 81: ...EB 8055 EN 14 5...
Page 82: ...14 6 EB 8055 EN...
Page 88: ...15 6 EB 8055 EN...
Page 89: ......
Page 90: ......
Page 91: ......